📋 Tender Overview
The Ministry of Transport, Mobility and Urban Agenda (Mitma) has formalized for an amount of 4.5 million euros (VAT included) the works contract for the modernization and improvement of the tunnels of Ortega Prados (MA-20 road) and Casabermeja 1, 2, 3 and 4 (A-45 motorway), in the province of Malaga. The corresponding announcement will be published soon in the Official State Gazette (BOE).
Although the tunnels currently have favourable operating conditions, it is necessary to carry out this action to adapt their facilities to the provisions of the Royal Decree on minimum safety requirements for tunnels of the trans-European road network.
Ortega Prados Tunnel
In installations and signaling, an adaptation of emergency lighting will be carried out, expansion of the existing ventilation system, replacement of the wiring that feeds the security equipment (ventilation, security lighting, public address, poles) by fire-resistant wiring, installation of evacuation signaling, fire extinguishers, a new radio communication system for emergency services and a new network of hydrants. In addition, variable messaging panels, traffic lights and lane closure barriers will be implemented.
Regarding the civil works, an element will be built to close the openings of the existing wall, a median passage and two doors in the dividing wall. The milling and replacement of the existing firm will also be carried out with the consequent repainting of road markings and replacement of headlamps. Likewise, a treatment has been carried out to eliminate leaks, consisting of a previous waterproofing of tree pits, manholes and drains, followed by a double sealing of the joints of the roof slab.
Casabermeja Tunnels
As for the facilities, an air quality control system will be implemented (tunnels 1, 2 and 3), the existing wiring that feeds the safety equipment (ventilation, security lighting, public address, poles) will be replaced by fire-resistant wiring (1, 2, 3 and 4) and a network of emergency posts (SOS posts) equipped with an emergency telephone and two fire extinguishers each (1, 2 and 3) and evacuation signage (1, 2 and 3). In addition, the facilities of all the Casabermeja tunnels will be integrated into the Calderón Cerrado Control Center.
New vertical signals, including traffic lights will be installed at the entrance to tunnels 1, 2 and 3. In Casabermeja 1 the beaconing will be reinforced by placing cylindrical milestones. Two gauge control systems will also be implemented, one for the Casabermeja 1 and 3 tunnels (installed in Casabermeja 1); and 2 and 4 (installed in Casabermeja 4).
Regarding the civil works, in the tunnels of Casabermeja 1, 2 and 4 an adaptation of the sidewalks will be carried out in addition to an improvement of the existing drainage in all of them. Also in all the tunnels of Casabermeja the firm will be milled and replaced with the consequent repainting of road markings and replacement of headlamps. In tunnels 1, 3 and 4 it will be necessary to implement new containment systems following the installation of the new signalling elements. Finally, in Casabermeja 3 auscultation devices will be installed.
The intervention is included in the Recovery, Transformation and Resilience Plan (PRTR), which includes investing up to 357 million euros (VAT not included) of the NextGenerationEU funds to modernize more than 80 tunnels and enhance the protection of wildlife and vulnerable users in the State Road Network through actions distributed throughout the national geography.