Adif has passed a new milestone in the development of the comprehensive renewal of the Ourense-Monforte de Lemos-Lugo conventional railway line with the new Oural Tunnel (1.9 km), which is being built parallel to the current one, in that will replace

The cale puts an end to the excavation in advance in the tunnel from each of its mouths, which has progressed at a rate of 5 m per day. In the next few months, the 'demolition' of the tunnel, with a section of 52 m2, will be completed, to then lay the track, which will be mounted on a slab on concrete and, later, the rest of the equipment: electrification, signaling, communications and protection.

The new tunnel will house a single electrified track and will have three emergency exits (one every 500 m), which will connect to the evacuation gallery, which will become the current tunnel, once the track and the rest of the equipment are lifted railways and is conditioned. One of the three evacuation galleries will be suitable for vehicles and the tunnel will have footpaths for maintenance or emergency vehicle access.

The Oural tunnel is one of the main actions of the comprehensive renewal plan that is being promoted on the Ourense-Monforte de Lemos-Lugo line (117 km), to which an investment of more than 550 million euros is allocated, mobilized in practically all of it, to reinforce its reliability and capacity and contribute to an improvement in the travel times of this route, which connects with the high-speed line in Ourense.

Progress at different points and areas of the line
The new Oural tunnel is being developed in parallel with the rest of the plan's activities: track renewal, infrastructure reinforcement (bridges and tunnels), electrification of the Monforte-Lugo section and adaptation to 25 kV of the current electrification of Ourense-Monforte, the renewal of signaling and telecommunications systems, the modernization of Monforte station and the construction of the new Lugo station.

Between Monforte and Lugo, road and infrastructure works are completed, after deploying 100,000 new sleepers and 130,000 m3 of ballast. The gauge has also been extended, to house the posts and electrification equipment, and 56 bridges and 7 tunnels have been reinforced.

Once its tracks have been renovated, it now moves forward on the lower passage between the platforms of the Monforte station; the adequacy of the rest of the stations; and in the pedestrian walkway in Sarria, which reinforces the permeability of Mazadoiro.

Between Ourense-Monforte, the scope of the actions was extended to expand the gauges in the 13 tunnels of the section and to match their performance to the European corridors. Renovation works in this area are progressing facing the great technical and planning challenge posed by the orography which makes, for example, that in some places it is necessary to dismantle railway installations for the access of machinery and to reassemble them afterwards.

In parallel, the assembly and adaptation of electrification and the installation of new signaling and telecommunications systems along the entire line are being addressed.

The renovation of the Ourense-Monforte de Lemos-Lugo line contributes to Sustainable Development Goals (ODS) 9 (sustainable, reliable and quality infrastructure), 7 (sustainability) and 8 (economic growth and job creation).

European funding
The construction of the new Oural tunnel, as well as actions related to the renovation of roads and infrastructures, the adaptation of bridges and viaducts and the expansion of gauges in tunnels and overpasses, count on European funding through the Recovery Plan , Transformation and Resilience. Funded by the European Union-NextGenerationEU.

🔍 Key Information

📄
Tender Reference No.
501312244
📅
Publication Date
02 Mar 2024
🌐
Sector
Railways
📝
Notice Type
News
📍
Location
Spain

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 02 Mar 2024
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Spain
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…