They will be placed within a period of 15 days and then begin the construction of the final pedestrian bridgesAs part of the third stage of the new Via Expresa Sur, a 5 km mega-project to reduce travel times, the Metropolitan Municipality of Lima (MML) began work on the installation of 4 provisional pedestrian bridges that will ensure walkability and safe access for residents. Then, within a period of 15 days, the construction of the final pedestrian bridges will proceed.
The first action of this project, executed by the Municipal Company to Support Strategic Projects (Emape), an entity attached to the MML, which will last around 4 months, began with the unloading of the modular metal structures of the 4 provisional pedestrian bridges.
The assembly of these metal bridges, which have 60 ml each, will be through a modular structure system based on the assembly of a walkway on the ground, placed on armed regulation bases, in addition to the accesses and towers for subsequent lifting with a crane. They are metal structures that are quick to assemble and are for exclusive use by pedestrians, who will be able to walk on them in total safety.
The provisional bridges will ensure the transitability of the residents during the development of the work until the completion of the execution of the definitive pedestrian bridges, which will be permanently installed.
ULTIMATE PEDESTRIAN BRIDGES
Once the installation of the provisional bridges is completed, the construction of the definitive bridges will proceed, which will be made of reinforced concrete, reinforced with metal structures in the steel beams and pillars.
These concrete bridges will be located at important intersections of the Via Expresa Sur, at the intersections with Jiron Garcia Garcia, Vicus Street, Dona Elsa Street and Jiron Esteban Camere, providing better accessibility to the residents of Surco.
They will also have concrete stairs, elevators, speed bumps at pedestrian crossings towards bridges, horizontal and vertical signage, ramps and road protection jersey walls.
Likewise, sidewalks and pedestrian paths will be built at the accesses between the auxiliary road and the main road that will improve the design of the Southern Expressway and, above all, will provide security.
WORK BEGAN FOR PUBLIC LIGHTING
Within this third stage, public lighting is also being implemented and work is currently being done on the stretch of Paseo La Castellana and Ayacucho avenues towards the Panamericana Sur with lights already installed. Work in the opposite direction will begin soon.
The work consists of the installation of wiring, poles and lights. In the following days it will be in the operational phase under the responsibility of the electricity concessionaire. It is estimated that they will be completed in April of this year.
STAGES VIA EXPRESS SOUTH
It should be noted that within the framework of the Via Expresa Sur mega-project, the construction of these definitive pedestrian bridges was planned as one of the execution phases. As is known, the Via Expresa Sur, continuation of the Via Expresa Luis Bedoya Reyes, has several stages. The first was the recovery of public spaces, basically the invaded properties, which began in 2024.
The second stage was the preparation of the auxiliary and main roads (trunks) with paving of concrete tracks, in addition to the works on Paseo La Castellana avenue, a transversal axis that needed to increase its road capacity and which is currently being carried out.
The third stage is precisely the one that has begun with the pedestrian bridges. The next phase will be the implementation of the viaducts for vehicular use that will be located on Surco and Los Proceres avenues.
Finally, road interchanges will be carried out on Avenida Republica de Panama and Panamericana Sur, in order to achieve faster and more efficient access.
The Via Expresa Sur mainly benefits residents of San Juan de Miraflores, Surco, Barranco, Villa El Salvador and others who previously did not have an additional mobility axis to Huaylas Avenue and Panamericana Sur. Therefore, this new route has decongested these intersections and travel times have been reduced from one hour to 20 or 30 minutes.