Recently, inaccurate and misleading information regarding the construction of the southern ring road in Bled has been appearing in the public domain. For the sake of providing objective information to the public, we want to clarify the facts and place them in a broader time frame.
The story of the regulation of traffic conditions in Bled has a long beard, and many different factors are involved at the national and municipal level. Pointing the finger in only one direction and overlooking the role of municipal authorities in (too) many complications is not the right way to find solutions.
The fact is that the financial resources for the continuation of this investment are guaranteed, and the state's intention to finally regulate the traffic situation in one of Slovenia's most important tourist pearls is clear and decisive. It is stuck elsewhere, namely in the acquisition of land, which is necessary for the construction of the southern Bled ring road. However, the role of the municipality and its bodies is by no means negligible, as one might conclude from some statements and comments.
The basis for acquiring land before construction, concluding compensation agreements and servicing the construction site during construction for the construction of the southern relief road in Bled is the Decree on the Municipal Detailed Spatial Plan for the Southern Relief Road in Bled (Ur. l. RS, No. 27/2012) , which was adopted by the Municipal Council of the Municipality of Bled at its 8th regular meeting on April 3, 2012.
For the area of ??the second stage, the procedures for acquiring the necessary land have not yet been fully completed, expropriation procedures are ongoing, and parallel negotiations are also underway. Three plots remain unresolved, namely plot no. 667/8, plot no. 667/6 and parc. no. 301/6, all 2191 Žele?e, of which two properties are owned by two owners (co-owners), the third property is owned by two other owners.
Since it was not possible to find project solutions that would be acceptable to both parties in the negotiation process with the mentioned owners, requests for the expropriation of these properties were submitted to the Radovljica Administrative Unit in June 2019. In August 2019, the competent administrative unit issued decisions on the initiation of the expropriation procedure for all four owners.
Within the expropriation procedures, an additional assessment was subsequently proposed and carried out for all three properties, according to the data for the building permit, with the aim of minimizing interference with these properties, as this was one of the owners' conditions for signing the contracts.
Since the owners did not want to enter into the described servitude contracts despite the reduction of the encroachment on their real estate, an additional request for restriction of property rights was submitted to the competent administrative unit in April 2022, on the basis of which the Radovljica Administrative Unit issued a decision in May 2022 to initiate the procedure for restricting property rights to these properties.
At the beginning of 2023, the investor (DRSI) realized that after numerous legal maneuvers by the owners or their lawyers, it would not be possible to conclude any agreement regarding the acquisition of the necessary real estate, so he addressed a letter to the Radovljica Administrative Unit to speed up the expropriation procedures and limit ownership rights in subject matters. Finally, in June 2024, he sent a general request to the Radovljica Administrative Unit to end open expropriation procedures and restriction of property rights, by issuing decisions on expropriation.
Representatives of the Municipality of Bled also participated in the procedures for presenting project solutions to the owners of land not yet acquired and in the search for other solutions acceptable to these owners. When looking for new project solutions, the Directorate of Infrastructure of the Republic of Slovenia always tried to find a compromise solution with the owners, but there was no positive response acceptable to both parties. The acquisition of all necessary land is a necessary condition for issuing a building permit. We especially want to emphasize that it is the mayors who can be very helpful in negotiating with their citizens. We have many good practices where mayors manage to find an agreement with their citizens.
Only after the acquisition of all necessary land can an application for the issuance of a building permit be submitted to UE Radovljica. Based on current behavior, it is not expected that the missing land will be acquired in 2024. As said, we will be very happy to receive help from the municipality or mayor, in solving this challenge. The actual process of obtaining a building permit at UE Radovljica takes about 9 months from experience.
The Investment Program (IP) will need to be amended after obtaining the amended Project for Implementation (PZI) project documentation. The amended project documentation will be completed in 2025, as long as there are no complications in the public procurement process. The construction of the entrance intersection at Betin, including the permit, will be completed in 2025. In the meantime, DRSI will try to complete the purchases at the next stage and apply for a building permit. The public contract for the construction of the next phase will be announced after obtaining the building permit.
Financial resources for all planned activities are already provided in the adopted budgets and also in the proposed budgets for the next two years.