📋 Tender Overview
The contractors of the tunnel works have exceeded the limit of the total excavated 15 kilometers of the main and service pipes of the second track.On the route of the second track work is intensively carried out every day. The construction of the second track is a demanding project that takes place over difficult terrain therefore it requires an experienced and efficient construction operative. Progress in tunnel works is slowest at the beginning later this excavation step gets longer. All 14 attack or excavation sites are now open and the work is going much faster than when the tunnels were dug.Based on the works carried out in 2022 the construction of certain tunnels shows savings due to a more suitable hill than we expected. In the case of the Mlinarji T7 and Stepani T3 tunnels where the breakthrough has already been carried out a saving of almost 1.5 million was recorded in the implementation of the primary substructure. An even greater saving is indicated in the construction of the kofija tunnel T8.