📋 Tender Overview
After obtaining a precautionary measure that provides security for the execution of the road work.Consorcio Vial Sama will execute the project for 608 million 578 thousand soles.
Provias Nacional completed the stage of perfecting the contract for the execution of the work: Improvement of the Boca del Rio-Tacna Highway in the districts of Tacna, Sama and La Yarada Los Palos in the province of Tacna, whose technical file was prepared by the Regional Government of Tacna. This occurred thanks to the signing of the contract last Tuesday, October 21.
Contract document No. 123-2025 contains the signatures of the head of the Provias Administration Office, Aldon Carmelo Yldefonso Sifuentes and Wu Xiaoxuan, legal representative of the Sama Road Consortium made up of the companies Construccion y Conservacion del Norte S.A.C. and China Gezhouba Group Company Limited Peru Branch.
This represents a great step for the region after delays in the administrative processes for the tender, carried out by Provias Nacional since June. This expansion of the highway will soon be a reality for the benefit of more than 300,000 Tacna residents and visitors who use this road to travel along the Tacna coast and to other regions of the countrys coast.
The contractual amount amounts to 608 million 578 thousand 824 soles and will be executed for 720 days. Of this amount, 10% must be given in direct advance, according to law, until November 5, date from which the execution of this double road should begin, which includes 47.52 km of highway, with two two-lane carriageways, berms, ovals, bridges, among others.
According to the Contracting Law, what must be ensured for the start of the work are five requirements: the contract with supervision, the total or partial delivery of the land, the delivery of the schedule and acquisition of inputs by the contractor, the delivery of the complete technical file and the delivery of direct advance within eight days after the signing. Of these procedures, the first two have already been completed.
It should be remembered that on October 1, through Official Letter No. 17128-2025-41-JECA/CSJLI-PJ, the Precautionary Measure granted by Judge Lenin Manrique Montoro Rodriguez of the Fourth Permanent Court Specialized in Administrative Litigation of the Superior Court of Justice of Lima was communicated, in favor of the company Construccion y Conservacion del Norte S.A.C., a member of the Sama Road Consortium, which orders the suspension the measures to declare the nullity of the process, which is why the signing of the contract has been achieved.
The work includes from the entrance to the urban area at Boca del Rio (Av. La Marina) intersection with the Costanera Sur highway, to the intersection of Av. Collpa and Av. Ejercito. According to the technical file, the traffic count is between 3,702 and 6,882 vehicles per day in its different sections, of which 80% are light vehicles, 14% heavy vehicles and 6% buses. With this project, 10 thousand vehicles per day could be reached.
The Regional Government of Tacna, especially the regional governor Luis Torres who promoted the project since his administration as mayor in 2015, welcomes the completion of this contractual process and the soon start of the execution of this project desired by the Tacna region that means work, security and development for this part of the south of the country.