Work contemplates 5 km of road improvement and will work as a way of avoidance in MoyobambaWith an investment exceeding 30 million soles, the Regional Government of San Martin, through the Special Alto Mayo (PEAM) project, has been executing the second stage of the asphalting of the Motilones Bridge - Cococho Sector - Puerto de Tahuishco, in the Moyobamba district.
This important work includes more than 5 kilometers of road improvement, which will directly benefit the population of the left bank of the May River and will facilitate connectivity with the city of Moyobamba and the Yantalo district.
During the execution of the works, especially in the area of entry to the Cococho sector, cutting and excavation work is being carried out, which has forced to temporarily restrict vehicular traffic. To do this, alternate routes have been enabled and marked by Tipinillo, Facchin and Punta de San Juan, allowing the circulation of vehicles while the intervention lasts.
Likewise, it has been reported that the drinking water and drainage service will be temporarily interrupted in some homes close to the works area. However, the replacement of these services is guaranteed once the corresponding work is completed.
It should be noted that the project contemplates four intervention sections, including: via Tahuishco port, cococho descent, crossing of the facchin sector to stage I of the asphalting and sector known as La Videnita.
In section 2, close to the port of Tahuishco, soil improvement work is already being carried out, with the placement of pedraplen to consolidate the land. Subsequently, progress will be made with the formation of the road platform, sub -base, base and paving. While in sections 2, 4 and 5 they will be paved with hot mixture of 2 inches thick. For its part, the cococho drop will be intervened with rigid concrete pavement of FC = 210kg/cm2, with a thickness of 20cm.
The work has an execution period of 10 months and will be integrated with the first stage of the asphalting already concluded, constituting a strategic avoidance route that will improve the fluidity of the traffic to the Tahuishco sector, Moyobamba and Yantalo. This project not only optimizes transitability and road safety, but will also promote local trade, boost tourism and contribute to the economic development of the region.
Moyobamba, September 15, 2025.