📋 Tender Overview
Rural Electrification That Transforms LivesIn one of the most important steps towards social inclusion and closing gaps, the Cusco Regional Government, through the Regional Management of Energy, Mines and Hydrocarbons, accelerates rural electrification in 13 rural communities in the district of Colquemarca, province of Chumbivilcas, which will directly allow more than 1,000 inhabitants to have permanent and safe electricity in their homes.
This project currently registers a physical progress of 75% and contemplates the creation of the electrical system with primary and secondary networks in the sectors of Quellomayo, Tiendachayoc II, Doble Cancha II, Infiernillo, Japon Center, Chamuray, Yanque Alto, Gran Chico, Mujumpata, Lambram, Corirumi, Huisuray II and Huaracco.
With an investment of more than 4 million soles, to date, 16 substations, 160 12-meter poles, 590 8-meter poles are being installed, in addition to 25 kilometers of primary lines, 42 kilometers of secondary lines and 242 home connections with an investment of more than 4 million soles.
The project is part of the commitment of the administration led by the governor, Werner Salcedo Alvarez, who has declared as a priority to close the rural electrification gap in the Cusco region by 100%, guaranteeing equitable access to this basic right.
With these works, the Regional Government contributes to improving the quality of life of more Cusco residents. It is a commitment of our management to increase the electrification coefficient in the region, stated the highest authority of the Cusco region.
For his part, the regional manager of Energy and Mines, Merciano Basilio Pelaez, highlighted the installation of power lines that meet quality and safety standards required by current regulations.