📋 Tender Overview
The National Railway Company CFR SA informs that between 27.08.2024, 09:00 - 05.09.2024, 21:00, repair works are being carried out in the carriageway area from the level crossing with the railway located at the intersection of railway PLOIE?TI SUD – MÈECIU, km 5+790, and DN1B – BLEJOI passage.
The works are executed by SRCF Bucharest, under its own direction and consist of:
drilling in order to raise the railway grade by approximately 30 cm to align with the existing road grade measured outside the area between the barriers;
dismantling the current Rosehill spring plate system;
breaking up the existing beams required to support the degraded Rosehill slabs and removing them from the line gauge;
dismantling the rail-transverse frame and stacking them outside the work site;
removal of broken stone at the new elevation of the path platform;
cleaning the existing drain and changing the granular filter material;
making the new platform of the path on the passage area with its stabilization and appropriate compaction;
new platform stabilization with semi-wet concrete;
bedding new Sparta stone layer 0.3 m thick;
creation of a 38 ml panel from the new thermally treated rail + new sleepers with Wosloch type fastening;
noise + stabilization;
creation and planning of concrete slabs.
During the period required for the repair works, road traffic will be diverted on route DN1A (Bolde?ti – Scaeni Pod Teleajen) – DJ 237 – DN1B (Bucov).
The circulation of passenger trains will be carried out according to the schedule displayed on the website of the private operator Transferoviar C?l?tori, carried out by boarding/disembarking the traveling public on a temporary platform in the premises of the Blejoi station.
CFR SA apologizes to road users for the inconvenience caused and thanks them for their understanding!