📋 Tender Overview
Los Cocos Avenue is one of the most affected by accumulated deterioration and neglects during the last 25 years.The Provincial Municipality of Piura (MPP) continues to run at a good pace the road improvement project in the Club Grau urbanization, reaching a physical advance of more than 30 %, according to the work resident, Oscar Velasco. The intervention has already allowed the placement of more than 2,500 square meters of the optimized slab on Los Cocos Avenue, one of the most affected by the accumulated deterioration and neglected during the last 25 years.
The project contemplates the installation of perally and submerged sardineles to improve rain drainage and extend the useful life of the road. This was one of the most critical areas of urbanization. With these works vehicular flow will be improved and the risk of floods will be reduced, said Velasco.
At the same time, at the height of the Municipal Library, the work continues with the use of heavy machinery, such as excavators, motor graders, rollers, dump trucks and cisterns, to reinforce the structural base of the road. These actions will allow a safer circulation for both pedestrians and drivers.
The intervention, which has the culmination date on June 8, also includes the renewal of sewer networks. These will be delivered with updated planes to the EPS Grau, guaranteeing its correct operation.
In total, the project includes 7,603.64 m2 of concrete slab, 67.77 m2 of asphalt pavement and the installation of sardineles. The investment amounts to S/ 3,357,205.83 and is supervised by the sub -management of works of the MPP, led by Ing. Yefrain Sanchez Nizama.
The official asked the neighbors for the temporal discomfort generated during the works. He also stressed that the work was reactivated after a brief suspension and advances within the planned schedule.
For their part, neighborhood leaders expressed their gratitude to municipal management, stressing that this work will not only improve the transitability and quality of life, but will also contribute to reduce the levels of insecurity in the area.
This intervention is part of a comprehensive strategy of recovery of the road infrastructure promoted by Mayor Gabriel Madrid Orue, with the aim of improving urban and mobility conditions in various sectors of the city.