📋 Tender Overview
The Road and Motorway Directorate (RMD) began to comprehensively rebuild the intersection of the D1 and D2 Brno South motorways including the D1 modification to a six -lane arrangement. The reconstruction of the traffic -loaded intersection will take two years. The price of work arises from the tender is CZK 3.2 billion without VAT. The D1 will be in two lanes all the time but drivers must prepare for significant traffic restrictions. In the following years the RMD counts on the extension of the D1 throughout the 30 kilometers long section between Kyvalka and Holubice.
MUK Brno South is one of the most busy grade -separated intersections in the Czech Republic. Up to 80000 cars including a high proportion of transit freight transport will pass through the current or future transport demands. The ramps and connecting stripes could be expanded in the future so that capacity can be further increased if necessary said Transport Minister Martin Kupka.
It is a key transport node which serves not only transit but also the locals for arrival in industrial zones and city districts. The descents and raids are newly designed to drive more smoothly than now. The intersection will be rebuilt from the four -leaf -leaf -leaf leaf -cloven crossing of the D1 and D2 motorways with the branches between the two highways will be exclusively straight or semi -played. This year in April the Brno-Centrum-Brno South section between 194 and 196. The D1 kilometer which was the first to expand the six-lane. The traffic situation that occurred on this section was complicated on both D1 and D2. The RMD therefore has now focused on the transformation of the Brno-jih intersection to be reduced as small as possible.
The D1 motorway is heavily burdened around Brno. The capacity of the four-lane arrangement is almost exhausted. Brno-centrum and Brno-jih intersections do not suit their design. The construction will also include noise barriers up to six meters high. A new less noisy type of asphalt is also used. Secret bridges will also grow so that the builders can also weigh the material at night.
The RMD plans to expand to six lanes near Brno a whole 30 kilometer -long D1 between Kyvalka and Holubice. It is divided into seven sections. The work wants to speed up as much as possible to make the restriction as short as possible. We would like to shorten the work as much as possible to do it at once. I think it paid off even in the modernization of the D1 motorway when it was originally supposed to be done after three sections a year and reconstruction would reach for many years. They rode but it was significantly shortened.
D1 MUK Brno south
Length: 1545 m
Number of building objects: 138
Contractor: D1 MUK Brno South: Report ZS Swietelsky Hochtief
Construction price: 3 196 383 193 CZK without VAT
noise barriers: 3 total length: 935 m
Bridge buildings: on Highway 7; on the branches of the MUK 7
starting implementation: 10/2025
Posting: 11/2027
Building length to put into operation: 25 months
The Road and Motorway Directorate is currently implementing a total of 263.3 kilometers of new buildings. These are 188.5 km of motorways and 74.8 km of class I roads.
The selection procedure contains another 126.7 km of highways and class I roads.
A complete overview of all upcoming and realized buildings can be found in the interactive map at www.rsd.cz.