📋 Tender Overview
The Road and Motorway Directorate (RMD) has opened two sections of the D6 motorway together 14.4 kilometers. These are buildings of burden relocation and bitter bypass. The RMD thus completed the construction of the D6 motorway in the Central Bohemian Region. So far the work has cost more than CZK 3.8 billion without VAT of which almost 60 percent will be paid by the European Union. The RMD also launched Kolesov where there are 62 places for trucks and 107 for cars.
View the gallery (2) By putting the sections of Horovicky and bitter in the total length of almost 15 kilometers we completed the D6 in the Central Bohemian Region. In the Karlovy Vary and Usti nad Labem regions another 27 kilometers of the D6 motorway is being built. Every new kilometer means safer and faster travel. The entire motorway from Prague to Karlovy Vary was finished in 2028 says Transport Minister Martin Kupka.
The Horesedel section follows the open part of D6 near Krupe last year in which the EU was significantly contributed to by the EU from the Program Transport 2021-2027. The section includes 12 bridges and a grade -separated intersection (MUK) Knezeves. There are six bridges on the section U Horovicky MUK Jesenice and two noise barriers 1.2 kilometers long. An interesting feature is the lightened embankment of the power plant slag in Pocerady. It was 300000 cubic meters. The specific weight of the lightweight embankment is one third lighter than the embankment from the soil. In addition the sections of the Horesel and Horovicky managed to connect during the construction. The original plan was that the Horeseledel section will be put into operation using temporary communication and connecting back to I/6. As the work on the bypass of Horovicky managed to accelerate by three months both sections opened at once and temporary communication was not needed.
The passage of the road I/6 by the municipalities of the Horesel and Horovicky was the worst sections that were now on I/6 because it was a traffic load in the villages. The completion of the D6 motorway from Prague to Karlovy Vary is a major priority for the RMD which is also visible in this highway. Altogether 15 kilometers.
Of the approximately 114 kilometers of connection between the capital and Karlovy Vary less than 43 kilometers of the highway remain to be completed. The highway connection of these two cities should be finished in 2028.
The buildings were co -financed within the program Transport 2021-2027 from the Cohesion Fund - OPD3.
D6 Horesedly relocation
Length: 9 200 m
Number of buildings: 94
Contractor: Eurovia Berger Bohemia bridge buildings
Construction price according to contract: 1 886 335 742 CZK without VAT
Price of construction after valorisation: 2 071 929 686 CZK without VAT*
Implementation: 2/2023
Posting: 9/2025
Building length to commissioning: 31 months
* including changes during construction
D6 Horovicky bypass
Length: 5 194 m
Number of buildings: 117
Contractor: Berger Bohemia Eurovia bridge buildings
Construction price: 1 509 482 066 CZK without VAT
Price of construction after valorisation: 1 747 817 520 CZK without VAT*
noise barriers: 2 total length 1220 m
Implementation: 3/2023
Posting: 9/2025
Building length to commissioning: 30 months
* including changes during construction
The Road and Motorway Directorate is currently implementing a total of 261.8 kilometers of new buildings. It is 187 km of motorways and 74.8 km of class I roads.
The selection procedure includes another 128.2 km of highways and class I roads.
A complete overview of all upcoming and realized buildings can be found in the interactive map at www.rsd.cz.