The same consortium executes the works that were considered completed despite pending workThe Freedom. - The Comptroller General of the Republic - CGR warned that the renovation of the Jaulabamba and Paibal bridges, located in the district of Huaso (province of Julcan) presents unexecuted work that was reported as completed, as well as constructive deficiencies and inconsistencies in the minutes of suspension of the contractual term, among other aspects. These situations represent risks that could affect the quality and timely execution of both works.
On September 11, 2025, the District Municipality of Huaso signed the contract for the execution of both works with the same consortium for S/ 950,186 and S/ 1,006,765, respectively. The execution period began on September 23, 2025 and, considering the established 60 calendar days, completion was scheduled for November 21, 2025. However, for each work, four deadline suspensions were approved in parallel, which postponed the completion date.
The contractor, through each construction resident and with the support of the contracted supervisions, reported that the physical executions ended on January 22 and 21, 2026, respectively. However, the Comptrollers Office showed that, as of January 29, there were still works not 100% executed (corresponding to different items) that were reported as completed and valued for payment by the District Municipality of Huaso.
Likewise, both works present construction deficiencies because some items would have been executed without meeting the technical specifications of the file and current regulations. For example, the placement of drainage pipes was poorly executed, since the rainwater discharge points are not operational; In addition, segregated particulate material was identified in the concrete of the approach slab of both bridges, among other aspects.
It was also evident that the construction resident of each project simultaneously carried out the same function in other projects located in different provinces of La Libertad and even in other regions, which would violate the State Contracting Law that requires the provision of full-time service. Likewise, inconsistencies were found in the minutes of suspension of the contractual period for execution of work, which generate controversy regarding the actual date of completion of the work.
The Control Visit Reports No. 002-2026-OCI/1762-SVC and 003-2026-OCI/1762-SVC, which include the above, were communicated to the district mayor of Huaso for the adoption of the corresponding actions. The documents are available in the Control Report Search engine and at www.gob.pe/contraloria
Freedom, February 26, 2026
Communications Management
PRESS RELEASE No. 200 - 2026 CG/GCOM