Technology group Wartsila has renewed its operation & maintenance agreement with Tasiast Mauritanie Limited S.A. a subsidiary of the Canadian group Kinross Gold Corporation for another three years. The agreement will ensure that the gold mines 60 MW power plant continues to operate reliably and safely to support the facilitys production schedules. The order with Wartsila was booked in Q2 2025.
Wartsila has been operating and maintaining the power plant since it was built in 2013. In connection with the power plant extension in 2022 an outcome-based element was introduced in the agreement focusing on delivering measurable results aligned with the mines commercial and operational targets in a sustainable way. The entire O&M agreement and the outcome-based element promote a shared responsibility between Wartsila and the customer in achieving these targets.
The mine is located approximately 300 kilometres north of Mauritanias capital Nouakchott. The mine relies on electricity from an isolated hybrid grid comprising of solar power and batteries with the Wartsila power plant providing both baseload power and spinning reserve to secure consistent energy for the hybrid grid.
Our operation & maintenance agreements cover every aspect of the power plants day-to-day operation and all related maintenance and administration tasks. By tailoring the agreement to the customers specific requirements we can deliver performance and lifecycle cost guarantees to add considerable value to the business comments Patrick Borstner Director Operations Africa at Wartsila Energy.
Wartsila supplied the equipment for the power plant in 2013 and extended the plant under an engineering procurement and construction contract in 2021. A new project to install two additional Wartsila engines is currently in progress.
Media contact for more information on this release:
Katri Pehkonen
Communications Manager
Wartsila Energy
Mob: +358 50 591 6180
Image caption: Wartsila has renewed its operation & maintenance agreement with Tasiast Mauritanie Limited S.A. a subsidiary of the Canadian group Kinross Gold Corporation for another three years. (c) Wartsila Corporation
All Wartsila releases are available at and at where also the images can be downloaded. Use of the image(s) is allowed only in connection with the contents of this press release. Wartsila images are available at .
Wartsila Energy in brief
Wartsila Energy is at the forefront of the transition towards a 100% renewable energy future. We help our customers and the power sector to accelerate their decarbonisation journeys through our market-leading technologies and power system expertise. Our solutions include flexible engine power plants energy storage and optimisation technology and services for the whole lifecycle of our installations. Our engines are future-proof and can run on sustainable fuels. Our track record comprises of 79 GW delivered power plant capacity and over 130 energy storage systems in 180 countries around the world. Over 30% of our operating installed base is under service agreements.
Wartsila in brief
Wartsila is a global leader in innovative technologies and lifecycle solutions for the marine and energy markets. We emphasise innovation in sustainable technology and services to help our customers continuously improve environmental and economic performance. Our dedicated and passionate team of 18300 professionals in more than 230 locations in 77 countries shape the decarbonisation transformation of our industries across the globe. In 2024 Wartsilas net sales totalled EUR 6.4 billion. Wartsila is listed on Nasdaq Helsinki.
🔍 Key Information
📄
Tender Reference No.
526406874
📅
Publication Date
19 Dec 2025
🌐
Sector
Energy, Power and Electrical
📝
Notice Type
News
📍
Location
Finland
📁
Documents & Downloads
No documents found
🏷️ CPV
No CPV found
Need help with this bid?
Our bid experts can help you find, evaluate & win more tenders.