The photovoltaic complex Dunamis went into operation on September 24, in the municipality of Santana do Matos (RN). Composed of 36 generating units, distributed in four plants - Dunamis I to IV - the venture has 117.54 megawatts (MW) of installed capacity.
The project, which is part of the new Federal Governments new Growth Acceleration Program (New PAC), has an estimated investment of R 569 million, contributing to the regions economic and social development.
The connection of the complex to the basic network occurs through restricted interest facilities, consisting of a range and a 230 kV transmission line, in a double circuit, approximately 100 meters long.
Environmental licensing was conducted by the Rio Grande do Norte Sustainable Development Institute and Environment (Idema-RN), which issued Operation Licenses (LO) to the plants and the associated transmission line.