📋 Tender Overview
* It is executed with an investment of 14.5 million soles and will benefit 3,723 inhabitants.The regional governor of Lambayeque, Jorge Perez Flores, made an inspection visit to the comprehensive work being carried out in the Fermin Avila Moron urbanization, in the district of Pimentel, where he noted important progress and spoke with the neighbors, who expressed their gratitude for the execution of a project that had been expected for more than three decades.
The project, identified with CUI 2405410, contemplates the improvement of pedestrian and vehicular traffic services, with an approximate investment of 14.5 million soles, directly benefiting 3,723 inhabitants.
During the supervision, the regional authority verified recent works such as the pouring of 22 cubic meters of premixed concrete on sidewalks, distributed in the different passages. In parallel, the placement of pavement in different sections is being carried out.
The work registers a physical progress of 28.72% and is in full execution, having restarted early on February 9, 2026, even above what was programmed in the schedule.
The intervention is comprehensive and includes the execution of flexible pavement on more than 23 thousand square meters, the construction of sidewalks, hammers and paver sidewalks, as well as side berms with block grass. Likewise, it includes concrete ramps for people with disabilities, garden beds and planters, green areas with grass and the planting of more than fifteen hundred seedlings between ornamental and forest species.
The project also incorporates urban furniture, such as garbage cans and reinforced concrete benches, in addition to a storm drainage system that exceeds 3,900 linear meters, which will allow structurally addressing the flooding problems that affect the area.
The governor highlighted that, despite the technical difficulties encountered - such as interference with existing networks - these have been solved through technical tables and coordination with entities such as EPSEL, guaranteeing the continuity of the work. We have had problems, but they have all been resolved. This work is not paralyzed and will be completed this year, he stated.
During the visit, the neighbors expressed their recognition of the current management. After more than 30 years of waiting, today we see that this work is a reality. We thank Governor Jorge Perez for complying with us, said a resident.
Finally, the regional authority highlighted the patience of the population and reaffirmed its commitment to completing the project within the current year, thus closing a historical gap in urban infrastructure for the Fermin Avila Moron urbanization.