📋 Tender Overview
The work is 61% complete and will be resumed in the coming weeks after the approval of the physical and financial modification.The Regional Government of Arequipa will continue in the coming weeks with the construction of the Paraiso de Chuca school in the Sabandia district, a priority work for this administration that considers education as the basis of development.
The educational institution presents a physical progress of 61% and is momentarily paralyzed due to the expiration of the contractual period. However, the physical financial modification 2 that is in process will allow the execution period to be extended and work to resume shortly, guaranteeing the completion of this important infrastructure that will benefit hundreds of students.
This project will transform the I.E. Paraiso de Chuca in a modern educational infrastructure of 1,959.80 m2, with large classrooms, administrative modules, dining room, kitchen, warehouses, control booth, passageways, ramps, stairs, sports slab and completely new furniture. This work is designed to provide 255 students at the initial and primary levels with safe, inclusive and appropriate environments for their learning.
To date, the execution of Modules 2, 3 and 4, as well as the Ramp and the Passage, has been completed. These environments are in the finishing stage (porcelain floors and application of primer to interior and exterior surfaces). Regarding Module 5, it is in the plastering stage. Likewise, the coverage of the sports slab is ready for the self-supporting coverage installation service to perform its service.
Education is and will continue to be the priority. The Regional Government of Arequipa has already made 31 modern schools a reality in different provinces and will continue to build more, so that no child or young person is left without a decent and safe place to learn and dream.