📋 Tender Overview
PROINVERSION has awarded 55 electrical transmission projects, for an amount of US$ 6,123 million, with an execution progress of 55.7% in the study period.Lima, January 20, 2026.- The Private Investment Promotion Agency - PROINVERSION presented its publication Balance of the electricity sector 2002-2024, which details the progress and situation of Public-Private Partnership (PPP) projects in electricity transmission and generation, awarded between the years 2002 and 2024.
During the presentation, Ivan Lucich, director of the Investor Services Directorate and head of the Data Analysis, Research and Strategic Intelligence Unit of PROINVERSION, pointed out that, between 2002 and 2024, the Agency has awarded 69 electricity projects for an approximate amount of US$ 10 billion.
The book is the first in a series of sector reports aimed at offering a comprehensive view of the Public-Private Partnerships (PPP) system; In addition, it makes visible the investors who have participated in the development of the projects and indicates the regions where these have been executed.
Lucich specified that, during the period in question, 55 electrical transmission projects have been awarded for an amount of US$ 6,123 million, with an execution progress of 55.7% (US$ 3,413 million).
In terms of electricity generation, 14 projects were awarded for a total of US$5,317 million, with an execution progress of 80.1%, equivalent to US$4,251 million. Likewise, he highlighted that, in the last two years, the award amount amounted to US$ 2,589 million, benefiting 18 million inhabitants.
Likewise, he maintained that, to date, there are already nearly 30 thousand kilometers of electrical transmission lines nationwide, which allows providing a reliable and continuous service. In this sense, he pointed out that the evolution of the interconnected electrical system has made it possible to increase the reliability of the electrical supply and have greater capacity to meet demand, without interruptions.
He added that PROINVERSIONs Data Analysis and Strategic Intelligence Unit has made it possible to identify investments aimed at closing gaps in electricity transmission and generation, contributing to improving the reliability of the system and strengthening sector planning.
In turn, the director of Electrical Projects at PROINVERSION, Anibal del Aguila, pointed out that the BOT concession model has made it possible to attract large companies to the sector. He indicated that this scheme, in which the private sector builds, finances and subsequently transfers the infrastructure to the State, opens long-term expectations, in line with the nature of infrastructure projects.
Likewise, he highlighted that the standardization of the bases and contracts has provided legal security to the investments, and added that the next step will be to scale the investment towards subtransmission or ITC (Complementary Transmission Facilities).
This is a challenge because they are projects that are very close to the populations, and that means that many times they will have to be done in underground sections, which implies that the projects need more field work so that they can be offered to the private sector, he warned.