View and embed a new video showing the latest progress as HS2 completes the last of 2011 concrete piles that form a key part of the foundations for the transformative new Curzon Street station in central Birmingham
Download the full set of new images showing the public spaces that will be built around the city-centre station.
Download more new images of the piling work and images of what the station will look like when complete.
Engineers working for the HS2 project completed the last of more than 2000 concrete piles that will underpin the foundations of Birminghams Curzon Street station this week as new images were published showing how the public spaces around the building will look.
Stretching for more than 400m between Moor Street station and Millennium Point Curzon Street will include seven platforms covered by an enormous arched roof inspired by the railway architecture of the Victorian age.
Construction of the new station is now well underway with engineers this week completing the last of 2011 piles. These concrete columns - each between 6 and 24 metres deep - have been sunk into the ground to support the foundations of the building.
HS2 Ltds Senior Project Manager Alistair Morgan said:
Once complete Curzon Street will be a new landmark for Birmingham - and provide a fitting city centre terminus for a railway that will improve journeys and free up space on the existing West Coast Main Line. These new images also show how it will be integrated into the rest of the city - with new green spaces better accessibility and onward public transport links.
Its great to see how much progress has been made on the foundation works and Id like to thank everyone whos been working so hard to get the job done. But weve still got a lot of work to do before the first passengers arrive and I look forward to seeing more significant progress in the year ahead.
At the front of the station passengers will pass through a paved station square edged by gardens facing Moor Street Queensway.
The new images released today show recent landscape design refinements that are being submitted to Birmingham City Council for approval. These include improvements to the management of rainwater drainage and improvements to the integration of cycling and walking routes connecting to the wider city.
They also show the tree-lined promenade with landscaped terraces that will stretch along the side of the building. A second entrance at the other end of the station - giving access to Digbeth and the east side of the city - will include a tram stop and taxi drop-off points as well as improved cycle access.
Next to the eastern entrance a new square will face the disused Old Curzon Street station building which was built in 1838. A new terrace and gardens will be created to the rear of the old station to complement the setting of the historic building.
The piling work which began in Sept 2024 was delivered by HS2s construction partner Mace Dragados joint venture (MDJV) working with Keltbray. As part of the project the team installed an 8m high retaining wall at the western end of the site and excavated 47000 cubic metres of material to create a level base for the station.
Once the earthworks were complete they brought in CFA piling rigs to install the reinforced concrete piles.
MDJVs Senior Project Manager Rodger Storey said:
Completing the foundation works for Curzon Street station marks a major milestone in the delivery of the project. The team is proud of the major achievement represented the extensive piling operation that forms the stations foundations.
With this crucial phase now finished we look forward to progressing the construction of the station building itself which will create further jobs apprenticeships and supply chain opportunities as activity on site continues to ramp up.
Following a short pause to allow Network Rail to deliver some essential maintenance to the railway viaduct alongside the site the final piles were installed during late February and early March 2026.
With the piling now complete the main focus has turned to preparing the way for the Digbeth extension to the West Midlands Metro - which will stop under the station on New Canal Street - and completion of the remaining foundation works.
In total more than 19000 tonnes of reinforced steel and 69000 cubic metres of concrete are needed for the sub-surface work with 7000 tonnes of reinforcement already installed and 29000 cubic metres of concrete poured.
Elsewhere on the site progress is also being made on the temporary office block that will be the nerve centre for the next stage of construction. At the peak of the work more than a thousand people are expected to be employed on the Curzon Street project both directly and via Mace Dragadoss UK supply chain.
Progress is also being made on the viaducts that will carry HS2 services into the city centre with the massive Curzon 2 viaduct almost complete. This 40-metre-high structure - the tallest on the project - will be slid into place across the Cross City line in the summer.
These structures are being built by another of HS2s contractors Balfour Beatty VINCI. In total more than 33000 jobs are supported by the construction of HS2 with the project recently celebrating the appointment of its 2000th apprentice a 19-year-old from Bordesley Green in Birmingham.
However there is still significant work to do across the whole 140 miles between London and Birmingham. Mark Wild HS2 Ltd Chief Executive is now leading a comprehensive reset of the project to ensure the remainder of the route is delivered as efficiently as possible and for the lowest reasonable cost.