📋 Tender Overview
The PECHP will implement the necessary actions to guarantee the supply of water resources.The Chira Piura Special Project (PECHP) informs the users of Piura and Sullana about the cutoff of the water supply planned to be carried out from December 1 to 15, 2025 by Maintenance of the Hydraulic Infrastructure of the Chira Piura Hydraulic System
The general manager, Eng. Luis Pretel Romero indicated that these activities are part of the Annual Preventive and Corrective Maintenance Plan of the Major Hydraulic Infrastructure of the Chira-Piura Hydraulic System, with the purpose of guaranteeing the efficient operation of this system.
The PECHP in coordination with EPS Grau S.A. will implement the necessary actions to guarantee the supply of water resources for population use through the Potable Water Treatment Plants (PTAP) of Sullana, Curumuy and El Arenal.
Among the actions of the work plan to be executed, the following are considered:
* Systematic Maintenance of the Daniel Escobar Diversion Canal, repair of slabs in poor condition of the hydraulic box of the canal from km 28+112.60 to km 28+265.00 (153 m) of the left bank of the canal.
* Maintenance on the right wall of the Sky Falls in the Main Spillway of the Poechos Dam.
* Maintenance of the Poechos system drainage system.
* Systematic Maintenance of the Main Canal under Piura Biaggio Arbulu, repair of slabs and painting of limnimetric sights.
* Maintenance of floodgates of the Bajo Piura Biaggio Arbulu Main Canal.
It is necessary to indicate that only for the Curumuy PTAP there will be a restriction of the water supply for 02 days necessary to be able to isolate the work area where the Daniel Escobar canal is going to be intervened, since there is the water resource that guarantees the water supply for the population, the total cut of the 15 days is for productive uses.
The population is therefore urged to make responsible use of drinking water on the days of said maintenance; recommending being attentive to the official statements issued in this regard and avoiding activities of high population water consumption to contribute to the continuity of the service supply.
The PECHP reaffirms its commitment to maintaining water security and the correct operation of the Poechos System, highlighting that these preventive and corrective actions are essential to guarantee the functioning of the infrastructure in an efficient and reliable manner, in addition to the supply of water for agricultural and population use.