President Ilham Aliyev participated in the opening of the Yeni Sangachal substation
President of the Republic of Azerbaijan Ilham Aliyev participated in the opening of the 220/110/10 kV Yeni Sangachal substation of AzerEnergy OJSC.
AZERTAC reports that Chairman of the Board of Directors of AzerEnergy OJSC Balababa Rzayev informed the head of state about the substation.
It was reported that this large-scale Green energy project envisages the integration of the 240 MW Shafaq Solar Power Station in the Jabrayil region into the energy system of Azerbaijan and the provision of electricity to the Sangachal terminal through the countrys unified energy system. The project was implemented within the framework of the cooperation agreement signed between AzerEnergy OJSC and bp company.
The 330 kV substation built by AzerEnergy in Jabrayil district in the first stage was inaugurated in May of this year with the participation of President Ilham Aliyev.
As the next stage of the project, a 220/110/10 kV Yeni Sangachal substation was built to supply the Sangachal terminal with renewable energy. With this, it will be possible to stop the gas-fired power plant operating at the terminal. In the future, solar electricity produced in Jabrayil district will be delivered to the Sangachal terminal through the countrys energy system.
As a result of the implementation of the project, the terminals annual electricity demand of approximately 500 million kWh will be met by renewable energy, 120-150 million cubic meters of natural gas will be saved annually, and carbon emissions will be reduced by 260-330 thousand tons.
Yeni Sangachal substation with a total area of 6.5 hectares is connected to the countrys energy system with four new 220 kV power transmission lines of 111 kilometers.
The power supply of the substation is provided by three independent sources, namely the 785 MW Janub and 385 MW Gobu power plants, as well as the 500 kV Absheron substation.
At the same time, five 110 kV overhead cable lines with a total length of 25 kilometers were built from here to the Sangachal terminal. In the next stage, it is planned to build two additional 110 kV overhead cable lines.
BPs Sangachal terminal (80 MW) and Shah Deniz Compressor Station (85 MW) will be supplied with electricity through this substation. Thus, the annual energy demand of both strategic objects of more than 1 billion kWh will be met through the unified energy system of the country.
It should be noted that advanced digital control panels, necessary equipment were installed in the substation, integration into the SCADA system was ensured, and a Control Center was built. The application of modern technologies and digital solutions has raised the reliability and stability of the substation to a high level.