presented the programming of works aimed at the completion of hydraulic works, preparation of technical files and formulation of projects for the year 2026.With the participation of the Regional Governor of Tacna, Luis Torres Robledo and the Vice Minister of Development of Family Agriculture and Agrarian Infrastructure and Irrigation, Orlando Chirinos Trujillo, Ordinary Session No. 01-2026 of the Board of Directors of the Tacna Special Project was held, where the programming of water projects and infrastructure works that will be executed during the period 2026 was presented.
During the session, the General Manager of the PET, Eng. Freddy Cohaila Mamani began the general presentation, giving way to the head of the Strategic Planning Office, Econ. Cesar Huertas Velasquez, who reported that the 2026 Institutional Opening Budget (PIA) contemplates the continuity of the main investments in execution, prioritizing strategic projects with regional impact.
Among the notable works are the reservoirs in the Cerro Blanco sector, which register an advance of 68.50%; the Cala Cala dam, with a physical progress of 4.61%; and the reinforcement of the Paucarani dam dam, which reaches 48.35% progress.
Likewise, in the sanitation sector, the drinking water supply project for the C.P. was considered. Boca del Rio, which will be executed under the Works for Taxes modality, with the approval of the Regional Council and the management of a budget modification for the updating, complementation and supervision of the technical file.
For its part, the Infrastructure Management presented the programming of works aimed at the completion of hydraulic works, preparation of technical files and formulation of projects for the year 2026. Among them, it was reported on the progress in the preparation of the technical file of the project Improvement of the water resource provision service for priority use of population consumption of the C.P. Boca del Rio, district of Sama, province of Tacna, whose execution began in January and will end in July present year.
Meanwhile, the Studies and Projects Management presented the formulation projects scheduled for 2026, highlighting the project Improvement of the drinking water service in sector 7 of the Coronel Gregorio Albarracin Lanchipa district, which will benefit more than 300 thousand residents of the district and the city of Tacna. This project registers 90% progress at the end of 2025, with the remaining 10% scheduled for 2026, corresponding to physical-legal sanitation procedures and accreditation of water availability.
Likewise, two formulation projects were presented, including the Improvement of missionary operational services in the area of monitoring and evaluation of water resources in the Uchusuma basin, through an intelligent management system for the automation and modernization of the PETs water infrastructure, an initiative that will allow the implementation of an automation system for the operation and monitoring of water in 39 PETs hydraulic infrastructures (between intakes, canals, reservoirs and underground wells). And the idea of the project: Creation of the storage, regulation and conduction line system at the head of the Caplina basin, Challaviento sector, for water service for irrigation, a proposal that seeks to guarantee water supply through a storage capacity of 4 million cubic meters in favor of nearly 5,000 residents of the districts of Calana and Pachia.
After the interventions of the officials and the development of consultations and recommendations by the members of the Board of Directors, the continuity of the scheduled work was ratified, based on budget availability. The session concluded with suggestions and requests for the analysis of water issues, which will be addressed in the next session, scheduled for this Monday, January 26.
The president of the PET Board of Directors, representatives of the Ministry of Agrarian Development and Irrigation (MIDAGRI), of the Regional Government of Tacna, as well as the president of the Board of Users of the Class A Groundwater Hydraulic Sector La Yarada participated in the session, representing the Boards of Irrigation Users of the region.