📋 Tender Overview
Works on the Tarnowskie Góry – Zawiercie railway line are coming to an end. A new platform has been built in Tarnowskie Góry, from where passengers can comfortably reach the airport in Pyrzowice. The result of the investment worth over PLN 660 million will be a new offer of train travel in the Silesian Voivodeship. The project, implemented by PKP Polskie Linie Kolejowe S.A., is co-financed from EU funds.
Comfortable journeys to the airport in Pyrzowice and, m.in, to the stations in Siewierz and Zawiercie will be provided by a new platform in Tarnowskie Góry. The facility was built and equipped with a shelter, benches, lighting and information boards. The platform will be adapted to serve passengers with reduced mobility. Communication will be facilitated by an elevator.
- We are building railway connections to Polish airports. The investment on the Tarnowskie Góry – Pyrzowice – Zawiercie line will ensure greater access to the railway and better communication. Freight transport will also be improved. This is an impulse for economic development in the region," says Andrzej Bittel, Secretary of State in the Ministry of Infrastructure, Government Plenipotentiary for Counteracting Transport Exclusion.
- The Tarnowskie Góry – Pyrzowice – Zawiercie connection will increase the accessibility to the railway in the Silesian Voivodeship. The airport's communication with cities in the region will be significantly improved. The project is also important for the development of efficient freight transport. The investment will allow for an effective combination of rail and air transport," says Ireneusz Merchel, President of the Management Board of PKP Polskie Linie Kolejowe S.A.
As part of the task carried out by PKP Polskie Linie Kolejowe S.A., a 30-kilometre section of the line between Tarnowskie Góry and Siewierz was rebuilt. Collision-free intersections were built, m.in. railway viaducts in Miasteczko ?l?skie over road 908, over the A1 motorway and in Pyrzowice over road 913. Freight train traffic is carried out to serve two sidings at the Siewierz station from the direction of Tarnowskie Góry. Thus, trains returned to this section of the line after 30 years.
Platforms were built at the new Pyrzowice Airport station and at the new Miasteczko ?l?skie Centrum and Mierz?cice stops. The Siewierz station has changed favourably, where a local control centre has been established, from which dispatchers will take care of the safe conduct of railway traffic along the entire line. On the Siewierz – Zawiercie section, 14 km of tracks were replaced, and the overhead contact line was built. Platforms were built at the Por?ba and Zawiercie stations and a new stop Zawiercie K?dzielów.
The result of the investment of PKP Polskie Linie Kolejowe S.A. will be a new offer of train travel - the most environmentally friendly public transport - to Katowice Airport from Tarnowskie Góry or Zawiercie. The estimated driving time from Zawiercie to the airport is 23 minutes, and from Tarnowskie Góry less than 20 minutes. Travelers from Katowice and Cz?stochowa will take about 1 hour to get there. Access to the railway will be increased by the Pyrzowice Airport station and new stops: Miasteczko ?l?skie Centrum, Mierz?cice, Zawiercie K?dzielów. Comfortable journeys will be provided by new platforms at the following stations: Tarnowskie Góry, Siewierz, Por?ba and Zawiercie. All platforms will be adapted to serve people with reduced mobility. The project will also enhance the role of rail as a clean transport in combination with air transport.
The task includes the reconstruction of a 30-kilometre section of the track between Tarnowskie Góry and Siewierz. The revitalisation and electrification covers a total of approx. 48 km of lines. Passenger trains will run at speeds of up to 140 km/h and freight trains up to 80 km/h. The investment includes 59 engineering structures and 38 rail-road crossings.
The value of the task "Revitalization and reconstruction of the partially disused railway line No. 182 Tarnowskie Góry – Zawiercie" is PLN 660 million net, EU funding under the Operational Programme Infrastructure and Environment is over PLN 500 million.
Currently, finishing works, acceptance and obtaining of certification are being carried out. The project is scheduled to be completed in the fourth quarter of 2023. The Tarnowskie Góry – Zawiercie line is scheduled to be put into operation in November. The launch of passenger connections is planned from the December train timetable.