📋 Tender Overview
Structure represented a total investment of S/. 3 million 740 thousand 115.72 soles.The regional government of Lambayeque, through the Special Project Olmos Tinajones - Peot, culminated the construction of the La Pilca pedestrian bridge, located in the district of Olmos, on the river of the same name. This infrastructure is ready for reception and close commission, which will directly benefit 412 settlers in the area.
The structure is at kilometer 9.50 of the Fernando Belaunde Terry road. It has a total length of 76 meters, a lane width of 2.20 meters and load capacity of up to 3 tons. The suspension bridge, with flexible steel board, has been designed not only for pedestrian traffic, but also to allow the passage of minor units, vital for daily transport and local economy.
The works also included the construction of riparian defenses, signaling and adequate accesses, ensuring a comprehensive and safe infrastructure. This work responds to the need generated by the change of the water regime in the area after the operation of the Olmos Project, which leads to the appeal transferred by the riverbed, today permanent.
Before the water transfer, the Olmos River was dry, and the population had no difficulty crossing it. However, the current constant presence of flow made the construction of a bridge indispensable that guarantees the continuity of traffic and connectivity between both margins.
The execution of this work was in charge of the Consortium SB, made up of the companies Constructora Andre Anghelos S.A.C. and concretta S.A.C., and represented a total investment of S/. 3 million 740 thousand 115.72 soles. Its prompt commission is expected to facilitate the transfer of people and the trade of agricultural products developed in the area.