The Lins Photovoltaic Complex went into operation on September 18, in the municipality of Sao Goncalo do Amarante, in Ceara (CE). The project is part of the Federal Governments New Growth Acceleration Program (New PAC), representing another strategic step in the expansion of the Brazilian electricity matrix through renewable sources.
Composed of 59 generating units, distributed across two plants, the complex has 182 megawatts (MW) of installed capacity. The Lins 01 Plant has 29 generating units, totaling 90 MW, while Lins 02 has 30 generating units and 92 MW.
The projects connection to the Basic Network will be carried out through the SE 230 kV Pecem II substation.
The environmental licensing process was conducted by the State Environmental Superintendence (SEMACE-CE), which has already issued the Operating Licenses (LO) for the plants and the line of restricted interest.
With the entry into operation of the Lins Photovoltaic Complex, the country further strengthens its prominent position in the generation of renewable energy, also contributing to the promotion of a fair and sustainable energy transition.
Special Social Communication Advisory - MMETelephone: (61) 2032-5759 | E-mail:
* * * * *