The General Comptrollers Office warned about risks in the continuity of the execution of the work to improve the drinking water and sewerage networks with home connections in the young towns of San Antonio and the expansion of San Antonio, in the district and province of Chiclayo. This is due to the contractors failure to comply with contractual obligations by not resuming work on the project that is in charge of the Provincial Municipality of Chiclayo (MPCh).

According to Report No. 058-2024-OCI/0425-SCC, which evaluated the period from August 12 to 16, 2024, the execution of the work began on April 4 of this year. However, the works were suspended by mutual agreement between the entity and the contractor from May 29 to June 27 due to health problems of the project resident.

Although the suspension period ended, the contractor did not resume the execution of the work. As a result, the MPCh issued two letters, including a notarial one, in which it demanded that the work be resumed within 15 days and warned that the contract could be terminated if the contractor failed to comply with the deadlines. However, the contractor failed to comply and the project remains paralyzed, with no decision having been made on the possible resolution of the aforementioned contract.

The contractor, in charge of the project for S/ 8,022,716 under a unitary price system and a 360-calendar-day schedule, argued that there are still queries and requests pending a response from the MPCh. The project has been paralyzed since June 28, 2024 by unilateral decision of the consortium. Despite this, the control report warns that the suspension of the execution period is not appropriate, since the current situation does not comply with the causes established in articles 142 and 178 of the Regulations of the State Contracting Law.

The construction consortium has also failed to implement essential safety, health and environmental measures at the work sites during the work stoppage, which endangers the safety of residents and pedestrians in the vicinity of the works.

The supervision contract was signed for the amount of S/ 423,000 and includes a calendar period of 375 days, of which 360 days correspond to the supervision of the work and 15 days to prepare the final settlement of the project.

The report has been sent to the Provincial Municipality of Chiclayo for it to take the relevant actions. Citizens can consult the complete report and other control documents on the official website of the Comptroller Generals Office www.gob.pe/contraloria.

🔍 Key Information

📄
Tender Reference No.
507892582
📅
Publication Date
03 Sep 2024
🌐
Sector
Water and Sanitation
📝
Notice Type
News
📍
Location
Peru

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 03 Sep 2024
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Peru
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…