📋 Tender Overview
Work is progressing on the execution of the San Juan de la Virgen bridge and its accesses, located in the province of Zarumilla, a road that was seriously damaged during the El Niño Costero phenomenon of 2017.
The San Juan de la Virgen Bridge and its accesses, located in the province of Tumbes, has an investment of S / 11.5 million and is expected to be completed before next December.
In the place you can already see the double rail platform and the works of laying steel, formwork and pouring of concrete in footings of retaining walls of the left access, upstream, placement of formwork, steel and pouring of concrete in upper slab of the sewer.
The workers with the machinery carry out the formwork of foundation and steel fitting in left access walls, the earthwork downstream of the bridge and will begin the construction of the accesses of the bridge accesses on both sides that will be developed with a length of 96 meters and 70 meters respectively.
As recalled during the El Niño phenomenon, the district of San Juan de la Virgen registered the largest number of roads destroyed and crop areas lost as a result of El Niño Costero in the department of Tumbes, the National Emergency Operations Center (COEN) reported at the time.
This work financed by the ARCC seeks to return the passability and connectivity to 4,572 inhabitants of the district of San Juan de la Virgen, Tumbes.