Investment project valued at S/ 287 million will improve drinking water service in six districts of Lima and CallaoThe Comptroller General of the Republic of Peru alerted the Lima Potable Water and Sewerage Service (Sedapal) that the delay in preparing the technical file to begin the construction of the Jacaybamba Dam, located in the province of Canta, could harm a total of 2,224,482 inhabitants of districts in the north of Metropolitan Lima and Callao, who are expected to benefit from a better drinking water supply service.
The project Creation of the Jacaybamba Dam was declared viable on May 20, 2022, with an amount of S/ 287,327,679.48, with the main objective of providing an adequate drinking water supply service in the area of influence of the Chillon Drinking Water Treatment Plant (PTAP), located north of Metropolitan Lima. Subsequently, on June 23, 2022, General Management Resolution No. 272-2022-GG was issued authorizing the start of the preparation of the final study and technical file of the project.
According to the Control Milestone Report No. 198-2024-OCI/0262-SCC, whose evaluation period was from October 21 to 30, 2024, it is noted that until October 30, 2024, the contracting for the preparation of the technical file had not begun, which is why the execution of the schedule established in the pre-investment study at the profile level that was declared viable by Sedapal is not being fulfilled. Said schedule indicates that the deadline for the preparation and approval of the technical file was established in December 2023 and the execution of the work was scheduled to begin in July of this year.
It should be noted that Sedapal only made the first call for the selection procedure to contract the consulting service for the preparation of the technical file on December 29, 2023, with a reference value of the contract for S/ 7,082,460.52, the process being declared void, due to not having any qualified offer, according to the Minutes of the Selection Committee of March 14, 2024.
In this regard, the control commission requested information from Sedapal on the current status of the project and the company reported that the second call for the selection process had not yet begun due to the existing risk for said investment due to a social conflict in the community of Cullhuay, located in the district of Huaros in the province of Canta. In this regard, the state company detailed that actions are being taken to address the aforementioned situation.
However, the report reveals that Sedapal was aware of this problem since April 26, 2024, without having concrete results until the date of issue of the control report, which denotes delays in the implementation of the project at the time scheduled in the pre-investment study.
This fact generates the risk of losing the validity of the viability of the project, whose maximum date to begin the preparation of the technical file expires on May 23, 2025 and then the pre-investment study that supported the viability of the project would have to be updated. Another risk is that the adequate supply of drinking water to the beneficiary inhabitants of the areas served by the Chillon PTAP is postponed.
Recommendations
The Comptrollers report recommends communicating these facts to the head of Sedapal so that urgent actions are taken to continue and complete the process of preparing the technical file and begin the execution of this important work that more than two million inhabitants of the northern area of Lima and Callao are waiting for.
FACT:
- The public investment project is expected to benefit the population located in three sectors of the Santa Rosa district, four sectors of Ancon, 20 sectors of Carabayllo, 20 sectors of Puente Piedra in Metropolitan Lima, as well as one sector of Mi Peru and 22 sectors of Ventanilla in Callao.
Infographic link: Sedapals delay in preparing technical file for Jacaybamba Dam would harm 2.2 million inhabitants
Visit us at:
Twitter: @ContraloriaPeru
Flickr: flickr.com/fotoscontraloriaperu/
Facebook: Contraloria Peru
Instagram: @contraloriadelperu
YouTube: ContraloriaTV
TikTok: @contraloriaperu
Lima, December 12, 2024
Corporate Communications Department
PRESS RELEASE No. 1377-2024-CG/GCOC