The Office of the Comptroller General warned the Ministry of Housing, Construction and Sanitation that the work to improve and expand drinking water and sanitary sewerage services in the urban area of the town of San Marcos, in the district of the same name, has an accumulated delay of 82%.
The work, whose investment amounts to S/ 134,475,300, is being carried out through the modality of Works for Taxes, thanks to an investment agreement between the aforementioned ministry and a private mining company. The works have been suspended since January 2024, according to the work notebook, due to the preparation of the technical file for major work works No. 4 and there is no schedule for the resumption of activities.
According to the concurrent control milestone report No. 120-2024-OCI/5303-SCC, until the date of issuance of the report, the supervising private entity has not issued a technical opinion regarding the first deliverable of the technical file for major works of work No. 4, within the deadlines established by the Works for Taxes regulations. This situation could lead to extensions in the completion of the project.
Deliverable No. 1 was referred on August 15, 2023 to the supervisory private company (EPS) to issue a technical opinion within a period of no more than 10 days. However, as of March 8, 2024, that is, more than 200 days later, it had not responded to the request of the Public Entity, authorizing or observing said deliverable, so the EPS could be subject to penalties.
The work began in March 2022 and should have been completed in June 2023 with a projection to start in June 2024. However, due to the suspension of work for almost six months, the completion date was rescheduled to December 2023.
During this period, the entity approved two technical files for Major Works (MTO) with binding deductive and rejected a third for lack of support; A fourth file is currently being prepared by MTO due to the need to relocate the wastewater treatment plant due to lack of land availability.
The report was communicated to the head of the Ministry of Housing, Construction and Sanitation for corrective actions to ensure the execution of the project. Citizens can also access the content of the document through the Control Report Finder.
The fact:
The investment agreement between the Ministry of Housing, Construction and Sanitation and a private mining company was signed in 2018 for S/ 15 million, and included the technical file, execution and supervision of the project; however, the investment amount was updated with the technical file approved by S/ 140,856,420. It should be noted that to date up to eleven addenda to the aforementioned Investment Agreement have been signed.