📋 Tender Overview
The Huallaga Central and Bajo Mayo Special Project, executing unit of the Regional Government of San Martín, received the work "Road Improvement of the Santa Rosa-Santa Fe-Limón-La Primavera-Nuevo Chanchamayo-La Divisoria-El Ponal Neighborhood Road of the Bombonajillo Valley, Bajo Biavo district, province of Bellavista", by the Bajo Biavo Consortium, putting at the service of 10,229 inhabitants.
The road has an extension of 19,549 kilometers, in addition to 4 reticulated bridges, which will serve for the population of the area to make their transfer in less than 45 minutes to Santa Rosa, since previously traveling the section was an adventure that took approximately one day.
Edwin Pérez Zavaleta, director of the PEHCBM Works Directorate, said that "the company was notified about the completion of the work, forming the committee for the reception of works by three members of the PEHCBM, Francisco Grandez Rengifo, May Hellen Reque Carrillo and Washington Valles Valera."
Precisely, last week, the director of works, the reception committee, the supervision and the contractor, made a tour, accompanied by the population that has become involved as part of the technical team, the respective test of the load of the bridges was done and with respect to diamond cutting in the structure of the bridges, This will indicate whether the work complied with the contractual terms.
In addition, a record was signed where the observations found by the technical team are reflected, the contractor will have a period of 45 calendar days to raise them, then the contractor will notify the institution and committee will again carry out the verifications and be able to conclude with the act.
At the same time, the point will be seen for the regional governor to carry out the inauguration of a work that began its execution in 2022, and its completion was far away, and thanks to the political decision of Walter Grundel it was completed with the execution.