📋 Tender Overview
The Regional Government of San Martin (Goresam) is executing the improvement of 29 blocks in two sectors of the Huayco neighborhood, of the city of Tarapoto. This work, which is carried out through the special Huallaga Central and Bajo May project (PEHCBM) with an investment of more than 33 million soles, includes the construction of ditches, sidewalks, sewers, cyclevias, asphalted, among other works.
Javier Sinti Flores, manager of the PEHCBM, together with his technical team, made an inspection visit to the work on the main roads involved: Jr. Martinez de Companon and Jr. Ricardo Palma, in addition to adjacent streets.
Details of Jr. Martinez de Companon:
In block 8, two Tapial homes were identified that will affect four meters of municipal retirement. The owners accepted the withdrawal, but request clarifications on who will assume the costs of demolition and replacement of the facades. The cycle path is planned from block 7 to 15, connecting to the cycle path of Av. Av. In the EI Miguel Chuqisengo Ramirez, the works will begin in May, with a contingency plan to guarantee the entry and exit of the students. Meanwhile, vehicular access to Mall de Plaza Vea, whose construction will end in November 2025, will be by Jr. Ramon Castilla.
Details of Jr. Ricardo Palma:
In compliance with the provisions of the regional governor, Walter Grundel Jimenez, the felling of trees will be avoided in the stroke, making a rethink to protect them. Some homes within public roads will be withdrawn with the consent of the owners. It should be noted that blocks 13 and 14 will have double lane, while the rest will be one lane. Heavy vehicles will be relocated once the works start. This project reflects the regional governors commitment to urban development and the improvement of the quality of life of the inhabitants of Tarapoto.