📋 Tender Overview
The Ministry of Transport and Communications (MTC), through its executing unit Provías Nacional, is working on the installation of the Cachinani modular bridge, located in the province of Lampa, department of Puno.
Due to the heavy rains in the area, the flow of the creek exceeded its flow, causing the undermining of the existing bridge structures. In view of this, the installation of a new modular bridge was managed and in this way, recover passability in the Rivera Coylata sector
This infrastructure is 27 meters long and is located at kilometer 17 of the 17 km of the Emp. PE 3SG – Vilavila – Palca – Lampa – Juliaca, in the section that connects with the towns of Palca and Lampa.
The installation work of the bridge is being carried out by the Directorate of Bridges and the Arequipa Zonal Unit.
The work carried out consisted of the demolition of the collapsed bridge, the placement of supports, the assembly and launch of the modular bridge. The installation work is expected to be completed by the end of May.
The installation of this modular bridge makes it possible for the residents of the area, most of whom are dedicated to livestock and agriculture, to relocate. The aim is to ensure the smooth flow of traffic so that citizens can continue with their daily activities.