📋 Tender Overview
The Comptroller General alerted the Decentralized Transport Infrastructure Project (Provias Descentralizado) about technical inconsistencies in the preparation of the final study for the project to improve the local road that connects the communities of Santa Rosa de Uyuni, San Francisco, Tarucani and Penon Negro, in the districts of Putina and Quilcapuncu, province of San Antonio de Putina.
The project, declared viable on October 14, 2019, was assigned to the Special Interventions Management of Provias Descentralizado, which contracted the services for the preparation of the final study on October 29, 2020. However, more than four years later, on December 12, 2024, the entity reported that the technical file had not yet been completed.
The Control Milestone Report No. 1827-2025-CG/GRPU-SCC points out technical inconsistencies in the final study, since only a 20.66-kilometer section of the local road was considered, despite the fact that the projects viability contemplates a total extension of 22.79 kilometers. This omission compromises the transitability of the beneficiary population and causes delays in the execution of the public investment.
In addition, approval was granted to the technical study without having key information, such as the state of the land and quarries, complete data in the basic engineering studies, as well as the descriptive report, measurements and budgets.
The report also identified deficiencies in the environmental impact statement and the detailed plans of the project.
The absence of these elements could generate subsequent modifications that would negatively affect the contractual execution of the work.
Likewise, an incomplete budget was detected in the final study, since essential items were not included for: the construction of ditches, the demolition of structures and management of interferences with mailboxes.
These deficiencies could generate additional costs, delays and modifications in the final study, affecting the deadlines and resources assigned to the project.
Given this situation, the Comptroller Generals Office urged the executing entity to adopt corrective measures to mitigate these risks and ensure compliance with the projects objectives.