After the incessant rains in the district of Huambo, province of Caylloma, Chinini sector; the culvert of channel 27 in the Pahuana ravine of the Chinini sector of the major hydraulic infrastructure of the Colca Siguas system has been clogged with stones and mud.
Autodema, the Board of Users of Majes and the district municipality of Huambo,
continue the work of desilting the sewer to mitigate the damage that could put at risk of collapse the aforementioned canal that feeds the Majes, Santa Rita de acronym and Colca Valley irrigation.
At present, the works represent
10 to 12% of the total material de-silted. The work began last week and will continue with the removal and/or movement of earth masses.
An excavator and a D8 crawler tractor from Autodema are used. There is also an excavator managed by the municipality of Huambo, Caylloma, which was donated by the regional government of Arequipa for this type of emergency event. A 15 m3 tipper, a low bed and a backhoe from Autodema and finally a backhoe from the user board.
The objective is to achieve the total rehabilitation of the infrastructure of the sewer of channel 27 and also that of the Chinini canal and intake, in order to recover its operation, which will allow maintaining the tranquility of the different inhabitants of the sectors of Majada, Capi Chico, Capi Grande, Marja, Jayaquima, Retiro; guaranteeing the availability of water resources for the crops of beans, corn, potatoes, among others, of the Majes irrigation and the lower part of the district such as Piche, Sajarhua.