📋 Tender Overview
Due to the breaches of the Southern Road Consortium for the rehabilitation and improvement of the Moquegua-Omate-Arequipa highway, the Ministry of Transport and Communications resolved, on May 31, the contract to be able to attend the paralyzed work.
It should be noted that on March 11, the Minister of Transport and Communications, Paola Lazarte, together with her technical team and the regional governor, Gilia Gutiérrez, toured the road to know, in situ, the problem. Subsequently, a technical table was installed to manage the restart of the road improvement work. However, the company did not comply with the provisions.
Among the reasons for revoking the aforementioned contract, it can be mentioned that, despite the fact that it was given a legal deadline to restart the work, it was not complied with and neither the restart plan nor the work schedule was presented.
The investment for the improvement of the road amounts to more than S / 521 million and has an advance of only 25%, approximately. To corroborate this percentage, since Monday, June 5, a multidisciplinary team of Provías Nacional is in the area in order to verify the evolution of the execution, together with justices of the peace.
The aforementioned road has 119 kilometers, consists of two sections and crosses the districts of Torata, Quinistaquillas, Omate, Coalaque, Puquina and annexes.
This road will boost the commercial flow in the south of the country, allowing citizens to move quickly and safely.
The MTC reaffirms its commitment to complete 100% of the asphalting of the road. Therefore, Provías Nacional will temporarily assume control of the passability of the road.
It is important to note that the Consorcio Vial del Sur has filed a precautionary measure to annul the termination of the contract made by the MTC. In this regard, the sector has already taken legal measures to prevent that.