The works of this infrastructure that will benefit more than 111 thousand Peruvians have an advance of more than 25 %.The Ministry of Transport and Communications (MTC) continues to work on its commitment to improve the countrys road infrastructure. Therefore, through the General Directorate of Transport Programs and Projects, it reports that the construction of the Arenita Bridge and its accesses in the province of Ascope, Department of La Libertad, has more than 25% physical progress.
This work, which represents an investment exceeding S/20 million, is located in the district of Paijan, at the height of Km 643 of the Panamericana Norte road. The intervention in the 1.08 km route. It will directly benefit 111 thousand Peruvians, who will have a more modern and safe route. The works consist of the construction of the Arenita bridge in the old road, replacing the previous structure, with a length of 60 meters above the Arenite creek and with its accesses between Km 633 to KM 634, approximately.
Likewise, the implementation of the auxiliary roads adjacent to the existing road will be executed, with a length of 473 meters on the south side and 407 meters on the north side, to provide an entry and exit access to the road of the Pan American Northern Pan American . Reinforced soil containment works, signaling, placement of road safety elements and expansion of transverse drainage works will also be built.
So far, beam enable work, steel installation and formwork of diaphragms beams have been executed. This infrastructure will improve connectivity and reduce congestion in existing pathways. It will also facilitate vehicular traffic, expediting displacements and reducing travel times.
With the construction of the second Arenite bridge and its accesses, transport conditions will be optimized and will boost local and regional trade, strengthening connectivity between the communities of freedom.