The construction of the Chimbote Bypass Highway, which will benefit more than 140,000 people in the north of the country, reached a physical progress of 82%, reported the Ministry of Transport and Communications (MTC), through the General Directorate of Transport Programs and Projects.
This important highway will connect the towns of Nuevo Chimbote, Chimbote, Coishco and Santa, in Ancash, and Guadalupito in La Libertad, covering about 40 kilometers of dual carriageway. Its objective is to solve the problem of traffic congestion in order to significantly improve traffic flow and facilitate commercial exchange between both departments.
Currently, the concessionaire has completed the construction of two bridges. The first, located on the Santa River, has a double structure 305 meters long. While the second, located on the Lacramarca River, with 45 meters, presents a design of post-tensioned beams and reinforced concrete slab.
The structures of the overpasses, located at kilometers 4, 12, 22 and 36 of the road, have also been completed. As well as the Vesique, Buenos Aires and Campo Nuevo ovals, and the drainage works of the San Antonio Drain.
Meanwhile, the Cascajal bridge, which covers an extension of 60 meters, is still under construction and aims to ensure the continuity of the project in this area.
The ministry led by Minister Raúl Pérez Reyes is committed to accelerating the work for its prompt entry into operation, which will optimize transport between the two regions and reduce both travel times and costs.
Currently, crossing from Nuevo Chimbote to Guadalupito takes between 1 and 2 hours, but with the new infrastructure, this time will be reduced to only 30 or 40 minutes approximately.
The Chimbote Bypass Road is part of the concession Road Network No. 4: Pativilca–Santa–Trujillo and Puerto Salaverry, managed by the concessionaire company Autopista del Norte S.A.C., which comprises approximately 356.21 km and covers the departments of Lima, Ancash and La Libertad.