📋 Tender Overview
The Comptroller Generals Office evidenced an economic loss of S/ 7,193,407 in the Regional Government (Gore) of Ancash due to deficiencies and irregular payments in the work to improve drinking water and drainage services in the Nueva Florida neighborhood, located in the district of Independencia, province of Huaraz. Fourteen former officials and public servants would have alleged criminal and/or administrative responsibility.
The work, carried out by the regional entity, began in December 2018 with an investment of S/ 11,359,566. The project included the construction of water collection points, conduction lines, a drinking water treatment plant (PTAP ), a reservoir, distribution networks, household water and sewage connections, as well as a wastewater treatment plant (WWTP), among other components.
Through the Compliance Audit report No. 056-2024-2-5332, it was revealed that in 2017 the Regional Government of Ancash approved the technical file of the aforementioned work despite the fact that it did not meet the technical conditions for its execution. since it did not have the feasibility of water and sewage services, the free availability of land and the authorization of the Ministry of Transportation and Communications to use the national road network.
The technical file presented activities and items with measurements and amounts that lacked support and an oversizing in the structure projected for the reservoir, aspects that increased the cost of the work by S/ 1,678,153. Despite this, they put out to tender the project and They awarded the award to a company that did not prove compliance with the qualification requirements.
Thus, in December 2018, the regional entity authorized the start of the work; However, there was no free availability of land for the construction of main structures, such as the drinking water treatment plant and the reservoir, whose construction was done on private land.
Likewise, the collection network works were carried out without the authorization of the Chavin Service Provider Company (EPS), nor with the land to build the wastewater treatment plant (WWTP).
Subsequently, they modified the layout of a section without carrying out the procedure established in the contracting regulations and paid for items that were not executed and/or carried out in a deficient manner. In addition, they approved deducting the WWTP when it is an essential component in the sanitation system, so the wastewater coming from the Nueva Florida neighborhood will not be treated.
During its execution, the work experienced three stoppages, the last of which was recorded in December 2022 because there were no authorizations from the District Municipality of Independencia and the EPS Chavin to carry out excavation and concrete replacement work, as well as mailbox splices, respectively.
These events showed that the investment made did not solve the social problem that justified the execution of the work, since it does not guarantee its operation to the detriment of the more than 2,888 inhabitants of the Nueva Florida neighborhood, who have seen the improvement of their quality of life postponed.
The report was notified to the Public Prosecutor for Crimes of Corruption of Officials and the Regional Governor of Ancash for the initiation of legal actions in order to determine responsibilities.