The comptroller general warned that the lack of maintenance to the hydraulic structures that make up the chira piura hydraulic system, such as the poechos reservoir and the daniel escobar and miguel checa diversion channels, could cause the deterioration of these constructions and affect the proper storage, conduction and distribution of water in the face of the emergency due to the water deficit that the region is facing.

According to the control visit report no. 038-2024-oci/0612-svc, the audit commission detected the exit of water from gates 1 and 2 of the daniel escobar canal intake, despite being closed, due to the wear of the seals that do not allow a hermetic closure to prioritize the supply of water resources to the curumuy treatment plant, from where water is collected to cover the demand of more than 575 thousand inhabitants of the districts of piura, castilla and veintiseis de octubre.

During the field visit, collapsed concrete slabs were found on the left bank of the aforementioned canal; sandbags had even been placed to prevent others from collapsing. added to this is the presence of excess material within the channel, the construction of artisanal dikes and expansion joints in poor condition.

Regarding the miguel checa canal, built before poechos, its waters flow over land and a large part of it filters along its route (more than 70 kilometers), which causes a significant loss of this vital resource; in addition, it is clogged with weeds, sacks and wood. at the beginning of the canal, near a hydroelectric plant, another water leak was seen, since the gates do not close hermetically either.

The situation is aggravated by the presence of motor pumps and other structures for the extraction of the little resource in the miguel checa canal, which causes a decrease in the flow destined for the population. this was verified at the querecotillo treatment plant, which had not received the liquid element for 20 days and, therefore, could not supply thousands of families in this district located in the province of sullana.

Sediments and outdated information
As for poechos, the presence of sediments, since its start-up (1976), has reduced its storage capacity. according to the study carried out in 2018, it can store up to 364.9 million cubic meters of water when its original volume was 885.

With data from 2018 that correspond to the latest bathymetry, the entity made decisions for the distribution and storage of the water resource, but with outdated information.

Last october, it was decided to keep the dam closed to farmers based on a preliminary result. despite being fully aware of the decrease in the reservoirs capacity due to the presence of sediments, the chira piura special project (pechp) did not carry out the necessary studies to allow the execution of mitigation actions during dry seasons.

🔍 Key Information

📄
Tender Reference No.
511498726
📅
Publication Date
05 Dec 2024
🌐
Sector
Water and Sanitation
📝
Notice Type
News
📍
Location
Peru

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 05 Dec 2024
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Peru
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…