Work has been suspended since July 5, 2024Lima Provinces. The General Comptrollers Office confirmed that the execution of the work to improve vehicular and pedestrian traffic services in the Nueva Estrella population center, in Huaral, was suspended due to health problems of the resident of the work.
The Control Milestone Report No. 19809-2024-CG/GRLP-SCC revealed that the resident of the work was absent for four days without any justification and only from the fifth day onwards the contractor presented a health justification. This caused the supervisor of the work to prevent the continuity of the works, as he did not have the key personnel for its execution.
According to the State Contracting Law No. 30225, the suspension of the execution period of a work occurs when events occur that are not attributable to the parties that cause the stoppage, without this implying the recognition of higher general expenses and direct costs. However, the absence of the resident of the work is a cause attributable solely to the contractor.
This fact would constitute the imposition of a penalty for breach of contract by the contractor. However, in addition to the initial term, the entity agreed to an extension of the residents period of absence from the work, based on medical recommendations.
Also, of the items approved by the resident and the construction supervisor at 100% execution, it was found that some did not comply with the requirements, such as the lack of asphalt primer on all streets and avenues, the absence of concrete in the curbs, the lack of asphalt joints on the concrete sidewalks and the lack of installation of railings on the walls. This generates the risk of payments being recognized for work not carried out.
Safety problems were also identified. The lack of delimitation with safety tape and caps in the uneven areas of the streets has compromised safety at work and puts the physical integrity of neighbors and passers-by at risk.
The report was communicated to the head of the entity so that, within the framework of his powers, he can take the preventive and corrective actions that correspond with the objective of ensuring the continuity of the project.