📋 Tender Overview
Mayor of Santa Cruz de Flores, Eng. Alexis Balcazar Huapaya, met with the General Manager of EPS Emapa Canete, Dr. Cesar Nieto Serpa, to sign the Construction Act of the electrical supply system for the Water Well of our town. The work includes the installation of the 10 kV utilization system, supply Ndeg 1093551 DM 65.00 KW, with an investment of S/ 423,599.00 soles.
This project, which will be executed within a period of 60 days, will improve the electrical supply to the water pumping station, directly benefiting the residents of Santa Cruz de Flores.
The District Subprefect, Mr. Raul Chumpitaz Chumpitaz, owners of the land where the work will be carried out, representatives of the contractor company and EPS officials also participated in the event.
This progress marks a significant step in the improvement of the districts water infrastructure.