The Canadian company Hatch, in charge of the first phase of the third stage of the Chavimochic Project, which includes the completion of the Palo Redondo Dam and the construction of the Third Line of the Viru Siphon, made its first technical visit to these structures, as well as to the intake and the sand trap of the most important Irrigation Megaproject in the country, which is being promoted by the Regional Governor of La Libertad, Eng. Cesar Acuna.
The Canadian technical delegation was made up of experts in dam safety, hydraulic design and execution, electromechanical structures, environmental, among other aspects necessary for the construction of a highly engineered structure such as the Palo Redondo Dam. The purpose of this visit was to learn about the status and magnitude of the works and then develop the plans that will guide the execution of the works. This is quite an important advance, evidence of all the efforts that the regional government of La Libertad has been supporting so that the Palo Redondo Dam can be completed as soon as possible, as is the commitment of our regional governor, reported the PECH Manager.
It is known that the physical progress of the work reaches 70%, lacking the filling of the dam, the placement of the concrete face, the electromechanical equipment, the injection system, the instrumentation, among other activities. This important visit will allow progress in the planning activities of all the works to be carried out to determine the final deadlines for the execution of the works, which preliminarily could begin in the first half of 2025 and be completed in 18 months, added the official.
Likewise, it was reported that the works to be carried out by the Canadian company are framed in the government-to-government (G2G) contract signed on April 30 of this year, which will guarantee the completion of the dam and the siphon. For his part, the Regional Governor signed on May 10 of this year the Agreement with Proinversion to complete the main canal and the automation through the Public-Private Partnership (PPP) modality. In this way, the complete execution of the Chavimochic works will be achieved, which will allow La Libertad and Peru to be a power in agroindustry and development of family agriculture.
In addition to these efforts, it is important to highlight the active participation of the Ministry of Agrarian Development and Irrigation (MIDAGRI) through the Subsectoral Irrigation Program (PSI), which is in charge of the works of the Dam and will be providing technical support for the completion of the works of this megaproject. The intervention of the PSI is important for the care and safety of the works, as well as ensuring that the hydraulic infrastructures meet the highest standards of quality and safety, where the PECH will be participating for the Regional Government, because it will receive the works for its operation and maintenance on a temporary basis once they are completed.
The Palo Redondo Dam will have a storage capacity of 401 MCM of water, a volume that will guarantee the supply of water resources for irrigation in the valleys of Chao, Viru, Moche and Chicama, both in the new areas and in those of improvement. In addition, the supply of drinking water for the city of Trujillo and its districts will be guaranteed, as well as the generation of electric energy.