The executive director of the Sierra Centro Sur Special Project, Paul Dax Prado Torres, visited the project Repair of reservoir, water intake, conduction line and irrigation canal in the Molino-Huanquispa irrigation system in the town of Huambalpa, district of Huambalpa, province of Vilcas Huaman, department of Ayacucho this morning.
During the visit, the director was able to verify in situ that the IOARR work is being carried out normally and is 40% complete. He was also able to talk with the workers who are working on the construction of the siphon line, in order to listen to their needs.
For his part, the project resident, Eng. Tito Rodriguez, mentioned that this reservoir will allow the storage of 1,400 cubic meters of water that will irrigate 275 hectares of agricultural land in the communities of Huanquispa, Amsarca, Limareq, Escor, Paccaypata, and Molino. He also indicated that work is being done on the construction of the siphon line, and it is also planned to install a 2 millimeter thick HDPE geomembrane; in order to waterproof the reservoir in order to complete it satisfactorily.
For his part, the director said today we have come to visit the Huambalpa reservoir, which has more than 6 million investments in general, the objective as executive management is to complete the project to deliver it to the beneficiaries so that the producers make use of this irrigation system so that they can improve their production levels of potatoes, corn, fruit trees, among others, and in this way guarantee the food security of this sector he said.