📋 Tender Overview
The Office of the Comptroller General alerted the National Urban Sanitation Program (PNSU) of deficiencies in the improvement and expansion of the drinking water, sewerage and wastewater treatment systems in the city of Huarmey, situations that would affect the continuity of the work, the quality of the infrastructure and the proper use of the investment.
The project, whose investment amount updated on 10/16/2023 amounted to S/ 220,270,234, began in September 2021 and is executed by the Ministry of Housing, Construction and Sanitation in Huarmey through the PNSU.
According to Control Milestone Report No. 29117-2023-CG/APP-SCC, with the extension of construction deadline No. 5, the execution period was extended until 07/31/2023, as well as the end of commissioning to 01/27/2024. However, according to the review of the valuations, there was a lower cumulative progress compared to the scheduled 100% 94.3%, 85.71% and 98.53% in relation to the main work, Major Work No. 1 and Major Work No. 2, respectively (as of October 2023).
In the inspection carried out, it was found that the discharge structure of the emitter of the Wastewater Treatment Plant (WWTP) has been executed in breach of the provisions of the technical file (shorter lengths of the side walls and inclination of the emitter pipe). This could have an impact on the discharge of treated wastewater into the Huarmey River, as well as generating stagnation of its course in dry seasons, to the detriment of the quality of the infrastructure and the environment.
At the Drinking Water Treatment Plant (PTAP) it was detected that the access ducts for the entrance to the raw water and treated water cisterns, as well as their pipes and overflow chambers have not been executed in accordance with the provisions of the hydraulic plans of the technical file and the regulations of the National Building Regulations.
In addition, the cisterns lack sanitary covers, ventilation pipes and protection at the mouth of the overflow pipes, which could affect the protection of the treated water during the operation and maintenance of the project, allowing vectors and rodents to enter. In addition, it puts at risk the physical integrity of the personnel in charge of the execution of the work and its subsequent operation.
It was found that the executor of the project has drilled holes in the lighting poles during the implementation of the exterior lighting of the PTAP, maneuvers that have damaged the corrosion and moisture protective coating provided for the concrete and the internal corrugated steel reinforcement, which transgresses technical standards and reduces its useful life.
In the item "Planting of trees" (1699 units) for use as a perimeter fence of the WWTP, the control commission verified that no activity had been carried out as of the date of the inspection of 10/11/2023. However, in July of the same year, the PNSU approved a physical advance of 50%, valuing 834 units of trees, after the approval given by the Supervisory Entity.
Thus, the control commission of the Sub-management of Control of Public-Private Partnerships and Works for Taxes, warns that there is no evidence that the PNSU, within the framework of its functions, has monitored the work of supervising the project, nor has it ensured that the supervisory entity is ensuring its correct execution in accordance with the contract.
The concurrent control report refers to the completion of other hydraulic and electrical equipment works and progress in the execution of the commissioning (period from October 20 to December 6, 2023). It is published in the Report Finder and was communicated to the PNSU so that the appropriate measures can be adopted.
DATUM
The project consists of the construction of a Drinking Water Treatment Plant (PTAP), raw and treated water pumping stations, cistern, reservoir, laying of primary networks and installation of 3070 meters. In addition, a Wastewater Treatment Plant (WWTP), stabilization lagoons, artificial wetlands and final wastewater disposal, 39.6 kilometers of sewage collectors and the installation of 3330 household connections.