Peru Continues Improve Tender

📄 Tender ID: 508970368 📅 Published: 03 Oct 2024

📋 Tender Overview

The works have a physical progress of 43%. The reconstruction works on Richard Cushing Avenue are progressing considerably and have accumulated a physical progress of 43%. To date, work is being carried out to improve the water and sewer system of the project, from Huancavelica Avenue to Bolognesi Avenue, according to the Deputy Manager of Works, Ing. Yefrain Sanchez Nizama.

In this section, the company in charge of the work has carried out excavation work for the installation of 480 linear meters of drinking water and 250 linear meters of sewerage. The official indicated the importance of this intervention that will benefit the residents of the area, since the current system of these basic services has exceeded its useful life.

The improvement is due to the current state of the water and sewerage networks. At the time of proceeding with the execution, the system was found to be in poor condition and this type of intervention is being considered. The work will be completed in three weeks, explained Sanchez Nizama.

As for what was initially planned in the technical file, the consortium is developing the formwork for curbs, concrete in hammers, trench excavation, among others. The sidewalks have been built and look modern in the first and second section of this important avenue of the city.

On the other hand, the official recalled that the management of Mayor Gabriel Madrid Orue prioritizes the construction of the roads with optimized MR45 slabs, because it is a material resistant to rain and the passage of vehicles. Our mayor is betting on optimized slabs that have a better performance to vehicular traffic and weather phenomena, he said.

For engineer Yefrain Sanchez there are three main objectives in the reconstruction of this avenue: the improvement of vehicular transitability, the recovery of pedestrian transitability and the adequate drainage system for evacuation of rainwater.

PROJECT GOALS
The project includes the construction of 4,207.39 square meters of optimized concrete slab, whose structural package is 30 cm. The execution of 2,417.04 m2 of sidewalks and hammers, 393.08 m2 of concrete ramps, 613.54 m2 of articulated pavement, 440.49 m2 of curbs, in addition to the installation of speed bumps, vertical and horizontal signage, leveling of mailboxes and the massive planting of trees on the avenue with various species of trees has also been contemplated.

The management of Mayor Gabriel Madrid Orue reaffirms its commitment to the progress and well-being of the city through the execution of this ambitious project. The recovery of the most important roads in the urban area is one of the essential objectives of the municipal government.

🔍 Key Information

📄
Tender Reference No.
508970368
📅
Publication Date
03 Oct 2024
🌐
Sector
Water and Sanitation
📝
Notice Type
News
📍
Location
Peru

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 03 Oct 2024
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Peru
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…