Construction work began on the 7-kilometre branch of Line 4 of the Lima and Callao Metro, which has a length of 7 kilometres. This important transportation system will connect underground with the New Terminal of the Jorge Chávez International Airport, located in Callao. This was reported by the Ministry of Transport and Communications (MTC), through the General Directorate of Transport Programs and Projects.

The branch line of Line 4 of the Lima and Callao Metro will have eight stations named: Gambetta, Canta Callao, Bocanegra, Aeropuerto, El Olivar, Quilca, Morales Duárez and Carmen de la Legua, located along Faucett Avenue, in the Callao region.

In terms of the progress of works, the Gambetta station, the first on the branch of Line 4 of the Lima and Callao Metro, has 54% of civil works, i.e. earthworks and structures, prior to the Architecture.

The Canta Callao station is also 16% complete and the Bocanegra station is 4% complete, in Civil Works.

Likewise, the branch of Line 4 of the Lima and Callao Metro will be interconnected through a tunnel with Line 2, at Carmen de la Legua Station.

According to the opinion of the concessionaire Metro de Lima Line 2, the Quilca station has been determined as the most suitable place to build an underground tunnel that will interconnect with the New Terminal of the Jorge Chávez International Airport. Meanwhile, the concessionaire Lima Airport Partners, for its part, has reserved an area within the new airport facilities for this purpose.

The MTC, through the concessionaire, estimates that the entire branch of Line 4 of the Lima and Callao Metro will be ready in four years. The investment is estimated at more than $1 billion.

This important transport system will have a fleet of seven trains, with 42 cars operated in the automatic 'GoA4' system, a fully automatic mode without human intervention involved, that is, without a driver.

Thanks to this underground train service, users will be able to travel from Gambetta station to Carmen de la Legua station in 11 minutes. Currently, this journey takes between 30 and 45 minutes by bus.

This great effort by the government and private enterprise will result in the continuation of one of the fastest and most modern transport services in Lima and Callao.

🔍 Key Information

📄
Tender Reference No.
502762610
📅
Publication Date
09 Apr 2024
🌐
Sector
Airports
📝
Notice Type
News
📍
Location
Peru

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 09 Apr 2024
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Peru
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…