The contract was signed on February 27, but as of May 16, the work had not started due to lack of delivery of the direct advanceHuacho. The Comptroller Generals Office warned that the Regional Government of Lima did not prevent the start of the project to improve drinking water services and installation of sewage and Wastewater Treatment Plant in the Populated Centers of Tres Estrellas, district of Aucallama - Huaral, for more than S/ 7 million, despite the fact that the contract with the company in charge was signed on February 27.

Report No. 024-2024-OCI/5344-SCC warned that on May 16 the control commission visited the place where the work will be carried out in the San Valentin town center and realized that it had not yet started.

In this regard, according to the works coordinator of the Municipality of Huaral, the project did not start because the entity does not disburse the respective work advance and its resources come from a trust (loan from another institution). Given this, as of May 16, 87 days had passed since the signing of the contract without the work starting. It should be noted that GORE Lima did not consider the constitution of a trust in the bases of the selection process.

In that sense, the Regulations of the State Contracting Law (RLCE) establish that the entity has 30 business days after signing the contract to process the trust and thus be able to grant the advance to the contractor; However, more than a month has passed and this payment has not been made, which prevents the start of work. Likewise, the RLCE indicates that the constitution of a trust is not a condition for the start of the execution of the work. It should be noted that the contractor could terminate the contract after 15 days after the deadline to establish the trust has expired, which gives him the right to request compensation for damages up to an amount equivalent to five times ten thousand (5/10,000). of the contract amount per day.

The situation exposed shows that the Regional Government of Lima would be violating the regulations, delaying the start of the work without any justification and affecting the timely fulfillment of the public purpose of the project, which could also cause the termination of the contract and request for compensation for damages by the contractor. The report was communicated to the regional governor of Lima so that, within the framework of her powers and competencies, she can adopt the corresponding preventive and corrective actions. Citizens can access the results of the report and other services, through the Control Report Search engine and portal www.gob.pe/contraloria.

🔍 Key Information

📄
Tender Reference No.
505170541
📅
Publication Date
21 Jun 2024
🌐
Sector
Water and Sanitation
📝
Notice Type
News
📍
Location
Peru

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 21 Jun 2024
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Peru
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…