📋 Tender Overview
The general comptrollers office warned of situations that may affect the functionality and quality of the work to improve the water service for irrigation in the san roque watson and cooperativa lateral canals in the tomaque, peca palacios and hornox localities, in the district and province of bagua. this project will benefit 231 farmers.
In order to create a preventive and/or corrective culture in the execution process of this work, the concurrent control milestone report no. 076-2024-oci/5331-scc was prepared, where it was noted that the wastewater generated in the peca palacios locality flows directly into the recently built san roque watson canal, because said locality does not have a public sewer system.
This fact has generated a local source of contamination, with the risk that during the operation stage, wastewater will be distributed to the beneficiary sectors and surrounding areas, distributing pathogens dangerous for agricultural irrigation, which represents a risk to the health of people who consume agricultural products irrigated with these waters.
Likewise, in the concurrent control milestone report no. 093-2024-oci/5331-scc, the control commission warned that the deadline for the execution of the work had ended; however, there were works that are still in the process of execution. despite this, the supervisor issued the certificate of technical compliance of completion of the work, a situation that would affect contractual compliance.
It was also detected that the works carried out present construction deficiencies such as the presence of pores, cracks, fissures, among other irregularities in the structures of the pedestrian and road bridges, failing to comply with the conditions established in the technical file, a fact that could affect the functionality and useful life of the work, in addition to generating payment for work not carried out or poorly carried out.
The adverse situations identified in both reports were notified to the head of the bagua sub-regional management so that he can adopt preventive or corrective measures to mitigate them. the reports are published in the control services report search engine.