Regulator warns that the CGR report intends for Ositran to observe the work, which would delay the opening of the countrys main air terminal. The Supervisory Body for Investment in Transportation Infrastructure for Public Use (Ositran) has received the Control Milestone Report No. 15827-2024-CG/APP-SCC, issued by the Comptroller General of the Republic (the Comptrollers Office) , where it is argued that the signing of an addendum is necessary for the construction of internal roads at the new Jorge Chavez International Airport (AIJC) and questions the execution of this work within the concession lands, as it has not been signed.

As is public knowledge, the internal circulation routes that Lima Airport Partners (LAP) is building at the AIJC will allow the connection with the provisional modular bridges that will serve as temporary access to the new air terminal. If the execution of the aforementioned work is paralyzed, as the Comptrollers Office intends, airport users and operators would be harmed, given that until an addendum is signed, in their opinion, the construction could not continue, delaying the date of its operation, scheduled for next December.

The Ositran clarifies that the construction of the internal access roads to the new Jorge Chavez includes an investment that is already projected for 2030 within the AIJC Master Development Plan approved by the General Directorate of Civil Aeronautics (DGAC) of the Ministry of Transportation and Communications (MTC), so the advancement of these works due to current need does not require an addendum.

It is also pertinent to clarify that Emergency Decree No. 009-2024 authorizes the MTC to contractually modify the Concession Contract to enable the construction of these internal roads in what corresponds to guaranteeing additional financing not provided for in the initial financing, which considered the not-yet-built Santa Rosa Bridge as an access route to the new air terminal, but an addendum is not necessary, in any way, for the construction and operation of works that the Master Development Plan already contemplates.

Ositran, as Regulator, has been actively working on supervision to guarantee that the works are developed in accordance with the established standards, under the fast track scheme, in which the design and execution activities of the work overlap. , which allows greater progress, since there is no approved technical file, but rather a design within a risk allocation framework, where both the design and construction risk are assigned to the concessionaire.

The Regulator warns that the CGR would be applying an inadequate reference framework (public works) to a self-sustaining concession, which is a completely different contractual figure, which does not require going through the National System of Multiannual Programming and Investment Management (Invierte.pe ), but has the Master Development Plan as the only frame of reference for the execution of investments.

Ositran reiterates its commitment to supervision within the legal framework of its powers and with transparency in the management of investments, which is why it will continue to work in coordination with the parties involved (MTC and LAP) to ensure compliance with the concession contract and the start-up of the new terminal on the scheduled date, for the benefit of the millions of users of said air terminal.

🔍 Key Information

📄
Tender Reference No.
505825574
📅
Publication Date
06 Jul 2024
🌐
Sector
Airports
📝
Notice Type
News
📍
Location
Peru

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 06 Jul 2024
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Peru
State / UT N/A
Tender Type Procurement News
Currency N/A
Similar Tenders
Loading similar tenders…