📋 Tender Overview
The Comptroller General identified deficiencies in the execution of the work to improve the urban mobility service in the Jauregui, Union and San Roman streets of Juliaca. Despite an investment of nearly 5 million soles, this work, which sought to improve urban mobility, presents delays, quality problems and possible risks to the safety of workers and the population.
According to the Concurrent Control Report No. 024-2024-OCI/0465-SCC, the project began on November 13, 2023 and was due to conclude on April 10, 2024. However, through the Infrastructure Management Resolution No. 081-2024-MPSR-J/GEIN, dated April 16, 2024, a 74-day extension was approved, which extended the term of the works until June 23. In addition, a second extension of 69 days was requested, which had not been approved at the time of the physical inspection carried out by the control commission.
Among the main irregularities identified are the following:
* The aggregates used for the concrete do not comply with the specifications of the technical file, which compromises the quality and durability of the work.
* The lack of security, signage, protection and order at the work puts workers and pedestrians at risk.
* A specific section of the project does not have the necessary land availability, which puts the completion and functionality of the project at risk.
* The work is 74.47% behind the original schedule, which could generate higher costs and postpone its operation.
* Workers not included in the technical file were hired, a situation that increases indirect costs and affects the efficiency of the use of state resources.
During the concurrent control of the urban mobility improvement work in Juliaca, nine adverse situations were identified that could affect the continuity, the result or the achievement of the project objectives.